ZXC10-BTS (V5.4) Installation Manual
1-4
1.2 Hardware Installation Flow
The normal operation of the ZXC10-BTSB I2 equipment is closely related to the
quality of the installation engineering. The equipment must be installed in a systematic
and standardized way, which helps to remove the equipment stability problems caused
by improper installation and improve the reliability of the system.
This manual focuses on the step-by-step installation method and procedure of the BTS
and its parts. It provides details to enable users to finish the equipment installation.
The indoor installation of the ZXC10-BTS focuses on the rack installation, the indoor
cable preparation and routing. Please follow carefully the steps below:
1. Fix the rack base to the rack;
2. Position
the
rack;
3. Mark and drill holes for bolts;
4. Fix
the
cabinet;
5. Install the power cable on the rack top;
6. Install the temperature and humidity sensor on the set top;
7. Install
the
T1
cable;
8. Install boards and modules inside the rack;
9. Connect the RF cable at the rack front.
The detailed hardware installation flow of the BTS system is as shown in Fig. 1.2-1.
This manual describes the specific installation procedure by chapters according to this
flow.
Содержание ZXC10-BTSB I2
Страница 1: ...ZXC10 BTSB I2 V1 0 cdma2000 System Base Transceiver Station Installation Manual ZTE CORPORATION ...
Страница 4: ......
Страница 8: ......
Страница 10: ......
Страница 22: ......
Страница 38: ......
Страница 54: ......
Страница 68: ......
Страница 104: ......
Страница 112: ......
Страница 140: ......
Страница 158: ......
Страница 172: ......