Chapter 5 Cabinet Installation
Note:
Ensure that the engineering over the cabinet (such as cable tray installation) is completed,
so that dust or metal scraps will not drop into the cabinet from the top during the cabinet
installation process.
Prerequisite
l
The related design documents are ready.
l
The drilling template (provided with the cabinet) is ready.
l
AN01 socket bolts are ready.
l
Tools such as cross head screwdriver, tape measure, spirit level, angle square,
powder marker, marker pen, percussion drill, vacuum cleaner, adjustable spanner,
torque spanner, socket spanner, claw hammer, punch, multimeter, and ladder are
ready.
l
Spacer shims, insulating gaskets, M12×90 bolts (an M12×90 bolt contains a spring
washer, a gasket, and an insulating washer) are ready.
Context
For the installation position of the cabinet in the equipment room, see
.
Figure 5-24 Cabinet Installation Position