NetNumen™ U31 R06 Hardware Installation Guide
Figure 13-1 Measuring Resistances Between Poles
2.
Switch on the
power distribution cabinet.
3.
Perform the following procedures after powering on the cabinet.
a.
Use the multimeter to check the PDU's output voltage.
The tolerance of the -48 V voltage is from -40 V to -57 V, the tolerance of the -60
V voltage is from -50 V to -72 V.
b.
Verify that the RUN/
indicator on the unified
is flashing green. For the
front panel of the unified
, see
Figure 13-2 Front Panel of the Unified PDU
1.
Control switch
2.
RUN/ALM
indicator
3.
COM indicator
– End of Steps –