Once the above has been verified proceed with the following checks:

•  Pump power cables properly connected to panel.

•  Float cables properly connected to panel.

•  Conduit connections to panel are properly sealed.

•  Thermal overload adjustments made in the panel.

•  After installing the pump into the containment area, with adequate submer-

gence, open the discharge valve fully. Start the unit using manual controls. 

If flow is appreciably less than rated performance, pump may be air locked. 

To expel trapped air, jog the unit several times, using the manual controls.

•  Have a qualified electrician take voltage and current measurements on the 

black wire of single phase or all three power wires of three phase with the 

pump running. Record these readings in the space provided in the 

“Owner’s 

Information” 

section on page 1 of this manual for future reference. 

After the preoperational functional test has been completed, system is ready 

for operation. Zoeller Pump Company requires completing a Start-up Report 

(ZM1074) whenever a system is started for the first time or after a system has 

had a significant change take place (i.e. pump replacement, overhaul, etc.). A 

copy of the Start-up Report should remain with the system for future reference.

Operation 

(continued)

ADJUSTMENT PROCEDURE

Pumps:  No adjustments are required other than assuring correct

 

 rotation.

Panels:  The thermal overloads in the panel  must be set to the F.L.A. rating on 

the pump nameplate (or refer to pump data sheet).

Floats:   Refer to the system drawing for desired location of each float function.

Valves:  Discharge valves should be placed in the fully open position. Systems 

should not be operated for extended periods of time with the discharge 
valves partially closed due to damaging the valve.

SHUTDOWN PROCEDURES

If a system is shutdown for more than six months, the following is recommended:

Pumps:  If pit is to remain dry, then the pump can remain in the pit. With the 

pump in the pit, it should be operated for five minutes once every three 

months. If the pit is to remain wet, the pump should be removed and 

stored as noted above.

Panels:  The panel should have all openings sealed to prevent moisture and dust 

from entering the enclosure. Prior to restarting system, the panel should 

be inspected for presence of moisture and any loose connections.

Valves:  Consult the valve/actuator supplier for information concerning these 

systems components.

 Repair and service should be performed by a Zoeller Authorized 

Service and Warranty Center only.

SAFETY PROCEDURES

 For your protection, always disconnect pump and panel from 

its power source before handling.

 Never enter the basin until it has been properly vented and 

tested. Any person entering a basin should be wearing a harness with safety rope 
extending to the surface so that they can be pulled out in case of asphyxiation. 

Sewage water gives off methane and hydrogen sulfide gases, both of which 

can be highly poisonous.

Installation and checking of electrical circuits and hardware should be performed 

by a qualified electrician.

Pump is never to be lifted by power cord.

 Unit must be flushed and disinfected, inside and out, prior 

to servicing.

GENERAL SYSTEM INSPECTION

Before the system is placed into operation, a system Start-up Report should be 

conducted by a qualified technician.

 Wiring and grounding must be in accordance with the national 

electrical code and all applicable local codes and ordinances.

LUBRICATION PROCEDURES

No lubrication is required.

If pumps are to be stored for more than six months, refer to short term storage 
procedure in the Operation section.

PREVENTIVE MAINTENANCE

Preventive maintenance is recommended to ensure a long service life from the 
product. Provided is a suggested maintenance schedule.

Every month:

•  Check for proper and unobstructed float operation.

•  Listen for proper check valve operation.
•  Duplex Units - Check for even operating times. Uneven times indicate a 

defective unit, float switch or control.

•  Inspect the panel for any presence of moisture in enclosure, loose connections, 

and general component condition. check out location and  condition of float 

switches.

Every year:

•  In addition to the monthly checks, the basin should be inspected and cleaned. 

Any defective components should be replaced. Inspect and remove any sand, 
debris, or mud present in the pump basin assembly. 

Every two years:

•  Check insulating oil in motor and seal chambers. Inspect oil for contaminations 

as follows:

•  Clear oil, no burnt odor - Oil, motor and seals are in satisfactory condition.
•  Dark oil, burnt odor - Pump motor has overheated. Check the motor winding resistance 

to ground. Ohm readings of 1 megohm or higher is required. If lower readings are 
present, return the unit to an Zoeller Authorized Service and Warranty Center for 
service.

•  Milky, emulsified oil - Seals have failed. Unit must be returned to an authorized 

service facility for service.

•  Dispose of the motor insulating oil properly if replacement is required.
•  Inspect power cables for damage or wear. Replace immediately if damage 

or wear is detected.

•  Inspect impeller for damage or wear. Replace as required by a Zoeller Authorized 

Service and Warranty Center.

DOUBLE SEAL PUMPS

•  Double seal pumps offer extra protection from damage caused by seal failure.
•  Oil in a motor housing and lower seal cavity must be checked when pump is 

serviced. If oil from the motor housing contains water or other contamination, 
both seals should be replaced during maintenance. Always replace with new 
factory recommended oil and service parts. All repairs must be made by  Zoeller 
Authorized Service and Warranty Centers.

Maintenance

© Copyright 2023 Zoeller

®

 Co. All rights reserved.

Содержание E611

Страница 1: ...l on 600 Series pumps Should further assistance be necessary please call our Product Support Department at 1 800 928 PUMP 7867 Table of Contents Safety Instructions 1 Limited Warranty 2 Performance Da...

Страница 2: ...ther liability in connection with our products Contact Manufacturer at 3649 Cane Run Road Louisville Kentucky 40211 Attention Customer Service Department to obtain any needed repair or replacement of...

Страница 3: ...ver sufficient voltage to the pump motor But more importantly they could present a safety hazard if the insulation were to become damaged or the connection end were to fall into the sump 4 Make sure t...

Страница 4: ...ump housing Be sure that this hole is cleared during any servicing 7 Vent gases and odors to the atmosphere through vent pipe per Local and State codes 8 Secure power cord to avoid entanglement with v...

Страница 5: ...for mounting these starting components 2 All pumps require overload protection in panel Use with approved motor control that matches motor input in full load amperes with overload element s selected o...

Страница 6: ...allation All single phase models require start capacitor run capacitor and relay in the circuit to start and operate properly These components can be purchased separately or prewired in Zoeller Pump C...

Страница 7: ...teringabasinshouldbewearingaharnesswithsafetyrope extending to the surface so that they can be pulled out in case of asphyxiation Sewage water gives off methane and hydrogen sulfide gases both of whic...

Страница 8: ...h Float travel obstructed Defective or damaged float switch Magnetic starter contacts shorted Air lock check vent hole E Pump operates but delivers little or no water Check for plugged Pump housing di...

Страница 9: ...ump Company http reg zoellerpumps com N mero de modelo ___________ C digo de fecha __________ N mero de serie Bomba 1 ____________ Bomba 2 ___________ Simplex N P de Panel ___________________________...

Страница 10: ...nto lodo alquitr n hidrocarburos derivados de hidrocarburos aceite gasolina solventes etc u otras sustancias abrasivas o corrosivas toallas para lavar o productos sanitarios femeninos etc en todas las...

Страница 11: ...s bombas sumergibles con capacidad para manejar desechos s lidos de diferentes tama os tengan un dise o para entrada en la parte inferior de modo que se reduzcan los atascos y las fallas del sello Si...

Страница 12: ...or de la bomba NOTA Elagujerodeber estardebajodelacubiertadel contenedorylimpiarseperi dicamente Durantelosperiodos de funcionamiento de la bomba se ver un chorro de agua que sale del respiradero Perf...

Страница 13: ...eber ncumplirsetodoslosdem srequerimien tos de la NEC consulte los art culos 500 501 y 502 y los dem s que correspondan Instrucciones de cableado Las bombas trif sicas no son autom ticas Para su opera...

Страница 14: ...631 641 651 Y 611 621 CON REL GE DESPU S DEL 10 1 07 Roc e una capa de aceite anticorrosivo a las superficies que no est n pintadas El impulsor debe girarse cada seis meses para mantener los sellos l...

Страница 15: ...da de seguridad que llegue hasta la superficie para poder sacarlas en caso de asfixia Las aguas negras despiden gas metano y sulfuro de hidr geno que pueden ser altamente t xicos Lainstalaci nyrevisi...

Страница 16: ...quema el fusible Voltaje incorecto Fuente de poder desbalanceada Rotaci n incorrecta del motor Carga baja o nagativa Temperatura del agua demasiado alta El impulsor o el sello est n pegados mec nicam...

Страница 17: ...CAUSENT des blessures corporelles graves la mort ou des dommages mat riels importants Il avertit des dangers qui PEUVENT causer des blessures corporelles graves la mort ou des dommages mat riels impor...

Страница 18: ...ter la responsabilit en notre nom pour nos produits Prendre contact avec le Fabricant 3649 Cane Run Road Louisville KY 40211 Attention Customer Support pour obtenir des r parations des pi ces de rempl...

Страница 19: ...gues ou de trop faible capacit ne fournissent pas la tension n cessaire au moteur de la pompe et ellespeuvent tredangereusessil isolantestendommag ousil extr mit avec le branchement tombe dans un endr...

Страница 20: ...ompe dispose d un trou d vent 7 Doit tre nettoy avant le etretien Les gaz et les odeurs rejet s dansl atmosph reparletuyaud ventd apr slescodeslocaux et nationaux 8 S curiser le cordon d alimentation...

Страница 21: ...les ressources n cessaires l installation de ces composantes de d marrage 2 Toutes les pompes n cessitent une protection de surcharge dans le panneau N utiliser qu avec une commande moteur quivalente...

Страница 22: ...er une d formation permanente Installation monophas e Tous les mod les monophas s n cessitent un condensateur de d marrage un condensateur de fonctionnement et un relai dans le circuit afin de d marre...

Страница 23: ...deux tre fortement toxiques L installation et la v rification de l quipement lectrique doivent tre faites par un lectricien qualifi Il ne faut jamais soulever la pompe par le cordon d alimentation AVE...

Страница 24: ...de blocage de l impulseur CAUSES FR QUENTES B Le moteur surchauffe et d clenche la surcharge ou grille un fusible Mauvaise tension Source d alimentation d s quilibr e Mauvaise rotation du moteur Press...

Отзывы: