Procedure:
1.
Set
product operation mode to
OFF
via the user interface (Section 8).
NOTICE: To switch off the product from the AC/DC power, the
AC/DC cables
must be
externally disconnected from the product and secured from being switched on again.
7.1
Annual Maintenance
NOTICE: During each maintenance interval, the following point must be checked.
Table 2: Maintenance in de-energized Condition (all 12 month)
MAINTENANCE TASKS
See
Section
Visual Inspection of Interior Area
Section
Section
Torque Check of Electrical Connections
Section
Check of Cable and Line Condition
Section
Section
Functional Test of DC Switch Disconnector
Section
Functional Test of AC Circuit Breaker
Section
Functional Test of Enable Switch
Section
7.1.1 Maintenance in De-energized Condition
7.1.1.1 Visual Inspection of Housing
Maintenance tasks:
a.
Check
the housing for visual defects, e.g. corrosion, discolouration or
damages.
In case of visual defects,
repair
these immediately.
b.
Check
if any labels e.g. safety signs on the control cabinet and power unit.
In case of damage or missing labels, please
contact
customer service
(Section 10).
7.1.1.2 Visual Inspection of Interior Area
Maintenance tasks:
a.
Open
doors.
b.
Check
the interior area for dust and water accumulation.
In case of dust and water accumulation,
remove
it from the interior area.
c.
Check
parts for discolouration or damage
.
In case of discolouration or damage, please
contact
customer service
(Section 10).
d.
Close
doors.
7.1.1.3 Cleaning of Fan and Air Ducts
Maintenance tasks:
a.
Clean
fans and air ducts.