Original Operating Instructions
BATI0XXX-ES-1-ZZZ-1
Decommissioning
O_BATI_0XXX-ES-1-ZZZ-1_V1.4_GB
Seite
53
von
60
8 Decommissioning
Procedure:
1.
Stop
the product (Section 5.3).
2.
Switch
off the AC/DC voltage externally and
secure
from being switched on
again.
3.
Disconnect
the AC/DC cables.
4.
Ensure
that no residual voltage is still present within the DC link (Figure 19)
by means of suitable testing equipment.
5.
Switch off
voltage measuring and supply voltage (Section 8.1) and
disconnect the lines.
6.
Disconnect
Ethernet cable and any other cables if they are still connected.
8.1
Disconnecting Voltage Measurement and Supply Voltage
By opening the fuses (-F31) in the control cabinet and fuses (-F2) in the power unit the
voltage measurement is disconnected from the grid (Figure 6).
The supply voltage is externally connected from outside and can be disconnected by
means of the external fusing.