GRANUDOS Touch, control unit
Index: 02
Date modified: 11/06/2019
OI No.: BA SW 010-02 Granudos Touch-Steuereinheit EN SCHW 8.docx
Page 9 of 43
4
Installation
See operating instructions Part 1 Dosing technology, regarding the respective dosing device.
for Granudos 10-Touch,
No.: BA SW 002
for Granudos 45/100-Touch, No.: BA SW 003
5
Commissioning
5.1
Commissioning, - comments
The work described here may only be carried out by trained specialist personnel from a specialist company.
Prior to commissioning, the installed devices must be checked for proper installation and leaks.
The device has been delivered with specific factory settings. The settings can be found in the operation data
sheet in
Section 9.4.
NOTICE!
Check all of the screw connections on the device. Plastic screw connections may only
be fastened hand-tight!
5.2
Commissioning tasks
The mechanical commissioning is now completed. The device is assigned with predefined parameters at the
factory. Please adjust the parameters to your pool, taking into account the required dosing performance and
target values.