Fig. 26
7.
Reverse procedure to install.
POWER SUPPLY BOX
COMPONENTS
Disconnect the
electrical power to the machine and
follow lockout / tagout procedures.
Shut off the gas
before servicing the unit and follow
lockout / tagout procedures.
All gas joints disturbed during
servicing must be checked for leaks. Check with a
soap and water solution (bubbles). Do not use an open
flame.
NOTE:
The power supply box must be removed to
access the following components: ignition control
module, transformer, R1 pump motor relay, and R2 fill
relay.
1.
Remove burners as outlined under GAS
BURNERS.
2.
Remove wire tie, and disconnect ignitor cable
from ignitor/flame sense electrode on the gas
pilot.
Fig. 27
NOTE:
When installing, replace wire tie to secure
ignitor cable.
3.
Remove lower basket lift cover as outlined under
COVERS AND PANELS.
4.
Disconnect all wiring harness connectors and
power cords from power supply box.
5.
Remove screw securing power supply box to
mounting bracket.
Fig. 28
NOTE:
Power supply box is slotted at the rear, and
secured by a hanging bracket (loose fit).
6.
Remove cover from power supply box.
Fig. 29
GR Series Gas Fryers with NCC Controls (formerly Tridelta / Built after 3/05) - REMOVAL AND REPLACEMENT
OF PARTS
Page 17 of
56
F35660