1.
Close the gas shut-off valve.
2.
Release the screw inside test nip-
ple "IN"
A
on the gas combination
valve , but do not remove, and con-
nect the pressure gauge.
3.
Open the gas shut-off valve.
4.
Check the static pressure; it should
be a max. 20 mbar +/- 1mbar.
5.
Switch on mains voltage and start
up the boiler.
Note
During commissioning, the boiler
can enter a fault state because of
airlocks in the gas pipe.
To reset press "
U
" key. The ignition
procedure will then be repeated.
6.
Check the inlet working pressure =
20 mbar.
&
Minimum working pressure = 12
mbar
&
Maximum working pressure = 20
mbar
Note
Use suitable test equipment, with a
resolution of at least 0.5 mbar, to
measure the supply pressure.
7.
Shut down the boiler, close the gas
shut-off valve, remove the pressure
gauge, and close test nipple
A
with the screw.
Commissioning and testing
(cont.)
52
Installation
58
62
670
GB
Содержание Vitodens 100
Страница 41: ...Opening the control unit housing Electrical connections 41 Installation 5862 670 GB Installation ...
Страница 82: ...A1 Main PCB A2 Programming unit Connection and wiring diagrams combi boiler 82 Designs 5862 670 GB ...
Страница 84: ...A1 Main PCB A2 Programming unit Connection and wiring diagram system boiler 84 Designs 5862 670 GB ...
Страница 88: ...Parts lists cont 88 Parts lists 5862 670 GB ...
Страница 89: ...Parts lists cont 89 Parts lists 5862 670 GB Service ...
Страница 90: ...Parts lists cont 90 Parts lists 5862 670 GB ...
Страница 91: ...Parts lists cont 91 Parts lists 5862 670 GB Service ...
Страница 95: ...95 5862 670 GB ...