62
B
A
C
D
Fig. 59
1.
Fold down heat management unit
A
. See
2.
Remove cover panel
B
.
3.
Close gas shut-off valve
C
.
4.
Loosen the screw in test connector
D
on the gas
train, do not unscrew. Connect the pressure gauge.
5.
Open gas shut-off valve
C
.
6.
Measure static pressure and record measured
value in report on page 162.
Set value: Max. 30 mbar (3.0 kPa).
7.
Close the gas shut-off valve. Remove the pressure
gauge and lock the screw in the test connector
D
.
8.
Fit cover panel
B
.
9.
Open gas shut-off valve
C
.
Filling gas condensing module and heating circuits
Fill water
According to EN 1717 with DIN 1988-100, as a heat
transfer medium for DHW heating, the heating water
must meet fluid category ≤ 3. This requirement is met if
water of potable quality is used as heating water. For
example, if additives are used, the additive manufac-
turer must specify which category the treated heating
water comes under.
Commissioning, inspection, maintenance
Measuring static pressure
5853335