Vertiv
|
NetSure 502NGFB Installation Manual (Section 6009)
|
Rev. Z
55
INITIALLY STARTING THE SYSTEM
Initially Starting, Configuring, and Checking System Operation when e/w NCU
Initial Startup Preparation
•
Ensure that all blocks except the last one in the “Installation Acceptance Checklist” on page 11 have
been checked.
•
Refer to the separate NCU User Manual supplied with your Power System for complete Controller
operating information.
•
Refer to the Configuration Drawing (C-drawing) supplied with your Power System for settings of
adjustable parameters.
Initially Starting the System
Procedure
1.
Apply DC input power to the system by closing the external DC disconnect(s) or protective device(s)
that supplies battery power to the system, if furnished.
Close the system’s internal battery disconnect circuit breakers, if furnished.
2.
Apply AC input power to the system by closing the external AC disconnects or protective devices that
supplies power to the shelf(s).
Note that the shelf requires two (2) AC input branch circuits.
The rectifiers start and supply power to the loads.
NCU Controller Initialization
Refer to
for locations of the NCU local indicators and navigation keys.
Figure 24:
NCU Local Indicators and Navigation Keys
Содержание NetSure 502NGFB Series
Страница 10: ...Vertiv NetSure 502NGFB Installation Manual Section 6009 Rev Z 10 This page is intentionally blank ...
Страница 37: ...Vertiv NetSure 502NGFB Installation Manual Section 6009 Rev Z 37 Figure 14 Controller RJ 45 Ethernet Port ...
Страница 45: ...Vertiv NetSure 502NGFB Installation Manual Section 6009 Rev Z 45 Figure 20 Battery Connections ...
Страница 85: ...Vertiv NetSure 502NGFB Installation Manual Section 6009 Rev Z 85 This page is intentionally blank ...
Страница 86: ...Vertiv com Vertiv Headquarters 1050 Dearborn Drive Columbus OH 43085 USA Section 6009 RZ 2020 ...