NetSure 502NGFB Installation Manual (Section 6009)
|
Rev. Z
40
To GMT Fuse Positions (List BA, NA, BC, LC and NC)
Load distribution (GMT fuses) and load return leads are connected to receptacles located inside the
Distribution Unit. Load leads are brought into the right side (as viewed from the front) of the shelf and are
accessible from the front of the shelf.
Observe correct polarity as shown in
when connecting leads.
a)
List 60 provides 12’ long, 16 AWG, load and load return leads that are terminated on one end with the
appropriate mating connector to plug into the system’s GMT fuse connector, and are left un-terminated
at the remaining end for connection into customer loads. Refer to SAG582136700 for P/N’s of the
mating connector if you decide to make your own cable.
Figure 16:
Load Connections to GMT Fuse Positions (List BA, NA, BC, LC and NC)
Front
GMT Fuses
and Safety Covers
Max. 10A
GMT Fuse Load
Distribution Leads
Connect Here
Mating Connectors and 12 ’
Leads provided with List 60
-48V on Left (Black Lead),
Return on Right (White Lead)
as viewed from side with door
closed
Содержание NetSure 502NGFB Series
Страница 10: ...Vertiv NetSure 502NGFB Installation Manual Section 6009 Rev Z 10 This page is intentionally blank ...
Страница 37: ...Vertiv NetSure 502NGFB Installation Manual Section 6009 Rev Z 37 Figure 14 Controller RJ 45 Ethernet Port ...
Страница 45: ...Vertiv NetSure 502NGFB Installation Manual Section 6009 Rev Z 45 Figure 20 Battery Connections ...
Страница 85: ...Vertiv NetSure 502NGFB Installation Manual Section 6009 Rev Z 85 This page is intentionally blank ...
Страница 86: ...Vertiv com Vertiv Headquarters 1050 Dearborn Drive Columbus OH 43085 USA Section 6009 RZ 2020 ...