[2] Crosswise Position of the Temple
[2.1] Left-hand side of the loom
(1) Loosen the bolts 2 (8 bolts) of a temple case 1.
(2) Move the temple case 1 so that a clearance “a”
between the left-hand side A of a temple ring 3
and a gripper 4 becomes 0.5 mm.
(3) Tighten the bolts 2 to fix the temple case 1.
[2.2] Right-hand side of the loom
(1) Pull the warp drawn through the reed toward you
at a right angle to a reed 5.
(2) Set the temple 7 so as to have the right-hand end
of No. 1 ring 8 of the temple 7 aligned to the
right-hand end 6 of the warp.
(3) After the setting, check that the right-hand end of
a fabric is held with the whole surface of No. 1
ring 8.
If not held with the whole surface, readjust.
When readjusted, readjust a cutter lever.
(4) To change the drawing width of a reed, loosen the
fastening bolts 9 (6 bolts) to move the temple 7 to
a prescribed position, then tighten the bolts 9 to
fix it.
M3. Temple
15