Before beginning:
Be sure to check the tightness of all bolts,
nuts and setscrews, which could have loosened
during shipping.
Rotate blower fan shafts by hand to make
certain there is no interference or rubbing
between components.
Verify installation surface is level before
proceeding with unit installation.
Locate mounting hardware:
Items included: Caulk, Caulk Tape,
Fasteners
Field Supplied Hardware: Anchoring studs
along with nuts and washers
Check all sections, of the unit, thoroughly for
assembly hardware. The assembly hardware
will be found packaged in either a clear plastic
bag or corrugated box.
NOTICE: There may be more than one
package of assembly materials
provided.
1. Anchor the stand on a level concrete pad
using studs or by other means. Each stand foot
pad needs to be secured.
NOTICE: For indoor equipment, the
stand must be enclosed (sometimes
height is increased.) A transition (by
others) must be made from enclosed
stand intake opening to the intake
damper or louver (a size variation may
exist.)
Flat & Level
Concrete Pad
Set in Place Stud or
Wedge Type Anchor
Flat
Washer
Hex Nut