46
Running A Test
transformer - exchange the primary with the secondary connections. If no
connection errors are found, there may be short circuit within the transformer itself.
Output Voltage Fail
A short or overload has been detected on the energization system preventing the
required output voltage from being applied to the transformer. Check for any
unexpected shorts in the connections or in the transformer.
In each of these cases, if the error occurs, the test will be aborted and will have to be re-run. Press “
CANCEL
” to clear
the error message, then re-run the test once the reason for the error has been determined and rectified.
8.3
Testing Stage 1 - Pretest stage
Once the test procedure has been started, the first stage of the process is to check the integrity of the test system.
The system check each voltage up to the voltage selected for the test, making sure that the system does not appear
to have the connections reversed and that the transformer under test is not drawing too much current for the selected
test voltage to be used. If it is unable to supply enough current for the transformer to be tested at the selected voltage,
it attempts to use the closest voltage it can without overloading the system. If the system considers that the
connections to the transformer are reversed (it measured a turns ratio of less than 0.8) it reports:
If this message box appears, check the connections are attached to the transformer correctly - that the “X” cables are
connected to the low voltage terminals of the transformer. Also check that there is no residual voltage on the
transformer, or that there is no significant voltage being induced onto the terminals of the transformer or the
connecting cables. Refer to section 3 for more information on routing the cables.
YES
This rechecks the connection on the current voltage - this should be chosen after
the connections have been checked, once you are certain that the transformer is
correctly tested.
CANCEL
This abandons the test and returns the system to the ready to start state.
CONTINUE
This overrides the determination process and moves onto the next voltage setting. It
should be used with a certain amount of caution. It could result in tripping of the
supply in the instrument. If there is a connection problem and the connections are
reversed, there is the possibility of damage to the transformer or the instrument.
Once the reversed connection process is completed, the system continues the pretest stage. It checks the
connections to the system an, if Auto 3Ph or automatic phase determination is selected, it attempts to determine the
correct configuration and phase displacement. If it is unable to do so it reports:
or
Содержание TTR 2795
Страница 1: ...Operating Instructions HAEFELY TEST AG TTR 2795 Transformer Turns Ratio Meter Version 1 4 ...
Страница 10: ...6 Introduction Maximum Roll Diameter Outer 50mm Inner 10mm ...
Страница 22: ...18 Connection and Setup Figure 11 Connecting to three phase BCT ...
Страница 101: ...Application Software APSW 2795 97 ...
Страница 111: ...Miscellaneous 107 14 7 Conformity ...