background image

3.696.5275.210

32

 

There may still be residual steam condensate (or boiler / high temperature 

water), this residual condensate / water could present a danger of injury in the coil 

that can run out during removal of the coil from the tank if sufficient time has not 

been allowed for cooling.
 

6.  Examine the heat exchanger coil for scale buildup and signs of leakage. If no leakage 

is  detected,  carefully  clean  the  excess  scale  from  the  coils  and  prepare  the  heat 

exchanger coil for installation. If leakage is detected between the coils and water in 

the tank, either repair the leaking coil(s) or replace the heat exchanger coil. 

7.  Remove the old gaskets and completely clean the mating surfaces. Install the two (2) 

new gaskets: one (1) between the tube face of the coil and the flange welded to the 

tank, and one (1) gasket with a divider to fit between the head and the tubesheet. 

8.  Carefully insert the heat exchanger coil into the tank. The coil should be installed so 

that the divider in the head lines up with the coil, and that the divider is parallel to the 

horizon. 

9.  After  assuring  that  the  heat  exchanger  unit  is  correctly  aligned,  clamp  the  flanges 

together and proceed with the torque procedure detailed in appendix A. 
a.  Lubricate the bolt threads and the nut faces with a suitable lubricant. 
b.  Insert the bolts through the flanges, then start and finger tighten the nuts. 
c.  Number all bolts so that torquing requirements can be followed. 
d.  Apply torque in twenty percent (20% [1/5]) steps of required final torque, loading 
   all bolts at each step before proceeding to the next step. 
e.  Use rotational tightening until all bolts are stable at final torque level.

   A minimum of two (2) rotations is usually required.

10. Reconnect the energy source inlet and clean steam outlet lines to the heat exchanger 

coil. If these lines were broken at an additional location to allow for removal of the coil, 

be sure to also tighten those connections. Follow recommendations contained in the 

manufacturers documentation, local codes, or accepted contractor practices as to the 

use and / or type of joint compound or sealer at the connections. 

11. Reconnect the small line leading to the energy source pressure gauge. 
12. Follow the startup procedures to put the unit back on-line. 

 

Carefully check all connections for any sign of leakage.

 

Inlet, Outlet, and Condensate / Water Return Line and Manual Shutoff 

Valves - Replacement 

If any of the inlet, outlet, return lines, or shutoff valves are damaged and must be replaced, 

follow the steps outlined below. 

 

The combination of electricity, steam, and water can pose a very dangerous 

situation. Turn off / disconnect all electric power before attempting any maintenance 

procedures.
 

1.  Follow the shutdown procedure (page 22) to take the unit off-line before attempting to 

replace damaged lines or shutoff valves. 

 

While it might seem feasible to replace inlet, outlet, condensate / water return 

lines, and shutoff valves without shutting down the entire unit, it is not advised. 

Unless the unit is completely shutdown, and the clean steam and energy source are 

isolated from the system, failure of a manual shutoff valve during the replacement 

process could result in serious injury.

Содержание CSM-C

Страница 1: ...86 05 CH Issue 4 CSM C Steam to Steam CompactCleanSteamGenerator Management Installation and Maintenance Instructions HTM 2031 approved The PED Directive 97 23 EC is repealed and replaced by the new P...

Страница 2: ...urezza La ghisa un materiale fragile in caso di caduta accidentale il prodotto in ghisa non pi utilizzabile Per informazioni pi dettagliate consultare il manuale d istruzioni del prodotto Rimuovere la...

Страница 3: ...d ariete Prevention of water hammer Scarico condensa nelle linee vapore Steam trapping on steam mains Intervalli di 30 50 m intervals Pendenza Gradient 1 100 Vapore Steam Gruppo di scarico Trap set Co...

Страница 4: ...ducts or re assembling after maintenance Evitare l eccessivo serraggio Utilizzare le coppie di serraggio raccomandate Do not over tighten Use correct torque figures Per garantire l uniformit del caric...

Страница 5: ...rom the bellows manufacturer Guide Guides Distanza breve Short distance Punto di fissaggio Fixing point Movimento assiale Axial movement Distanza media Medium distance Tiranti limitatori Limit rods Pi...

Страница 6: ...3 696 5275 210 2...

Страница 7: ...g Power Input Lines 20 Installation Completion 21 Commissioning 21 Commissioning Procedure 21 Shutdown Operating Procedures 22 Contents Page Emergency Shutdown Procedure 22 Daily Operation Steam Gener...

Страница 8: ...spiratory system Referring to the Installation and Maintenance Instructions name plate and Technical Information Sheet check that the product is suitable for the intended use application The products...

Страница 9: ...ammable materials substances hazardous to health extremes of temperature Hazardous environment around the product Consider explosion risk areas lack of oxygen e g tanks pits dangerous gases extremes o...

Страница 10: ...to work All work must be carried out or be supervised by a suitably competent person Installation and operating personnel should be trained in the correct use of the product according to the Installat...

Страница 11: ...ther rubbish and consign it to a landfill site Viton Waste parts can be landfilled when in compliance with National and Local regulations Parts can be incinerated but a scrubber must be used to remove...

Страница 12: ...the Compact Series Steam Generators only in the supply of a full clean steam package will Spirax Sarco assume responsibility for the unit and the clean steam produced Alternately Spirax Sarco will on...

Страница 13: ...o the exterior of the pressure vessel and individual specification tags on pressure related components and controls for design specifications and maximum pressure for the unit Controls Spirax Sarco St...

Страница 14: ...U Bundle heat exchanger is manufactured with stainless steel AISI 316L tubesheet the connection piece used to mount the U bundle in the generator body is also constructed from AISI 316L Nameplates A...

Страница 15: ...and 500 mm above the unit It should be located on a level surface no more than one half degree of slope capable of supporting the total weight of the unit when filled to capacity The unit should be mo...

Страница 16: ...2 If the unit has been in operation allow the clean steam and water in the tank as well as all components and surfaces outlet steam lines energy source inlet lines etc to cool 3 Ensure that all power...

Страница 17: ...uck placing the forks on the underside of the frame structure in a central position thus evenly distributing the units weight and providing a stable balanced load refer to Fig 3 If crated when shipped...

Страница 18: ...with drawings that indicate the location and specifications for each connection that must be made In addition the drawings indicate the flow direction of both the steam and primary supply Connecting t...

Страница 19: ...ould be installed downstream on the generated clean steam line for isolation purposes in case the unit must be disconnected from the system The shutoff valve should be in the closed position and remai...

Страница 20: ...x Sarco Connecting the Primary Supply Steam Possible injury or death Assure that a manual shutoff valve is installed upstream in the steam line energy source and that it is functioning properly If any...

Страница 21: ...ated from the system The condensate shutoff valve will prevent back flow of condensate if the line is disconnected Piping the Safety Valve to Vent and drain All Spirax Sarco Compact Steam Generators a...

Страница 22: ...ined in the Installation Manual for the component for specific piping instructions Note For all pneumatic connections the use and or type of joint compound or sealer on the joint should be determined...

Страница 23: ...3 696 5275 210 19 Note Blowdown connection should be performed in accordance to local codes accepted practices or the requirements of the installing contractor Fig 10 Blowdown...

Страница 24: ...the nameplate voltage and frequency Attention unused wires in conduit must be grounded at both ends to avoid a possible shock hazard caused by induced voltages Note if the environmental conditions bri...

Страница 25: ...ondensate Pre Commissioning Inspection 4 Check all joints within the generator are tight 5 Note Orientation of the feedtank level transducer should be horizontal 6 Check the Electrical connections 7 C...

Страница 26: ...y or in the unlikely event of a malfunction within the Clean Steam Generator 1 Press Remote Stop Button either on front panel or remote location 2 Close plant steam supply isolation valve 3 Close clea...

Страница 27: ...k must be recirculated The feedwater will be recirculated to minimise stagnant water within the system and to assist in the removal of non condensable gases Water within the feedtank should be maintai...

Страница 28: ...ller will feed water to the generator when the level falls under the setpoint level and will stop feeding when the water level reaches the set point The level controller also has a low water alarm pos...

Страница 29: ...er sends the 0 10 V signal equivalent to 0 100 mbar range to PLC control unit which elaborates it and consequently transmits the ON OFF control signal to the piston control valve on the feed water lin...

Страница 30: ...e is correct Check that PAV solenoid valve is energised Operate manual override on solenoid valve to check operation of valve Manually operate valve via tank synoptic screen on controller Water level...

Страница 31: ...Isolate plant steam supply and inspect valve seat for damage see appropriate instruction manual Steam supply pressure exceeds maximum differential pressure of valve Check plant steam supply pressure...

Страница 32: ...uction manual Water level transducer is damaged and giving a false reading Replace level transducer See page 40 of this manual Steam from a second generator is back feeding into generator shell and co...

Страница 33: ...Service Department Controller Touch Screen is blank and does not respond when touched Power has failed Check electrical power is on Contact Spirax Sarco Service Department Generator is unable to main...

Страница 34: ...d controls or junction boxes follow the steps listed below The combination of electricity steam and water can pose a very dangerous situation Turn off disconnect all electric power before attempting a...

Страница 35: ...es 1 Follow the shutdown procedure page 22 to take the unit off line before attempting to remove and inspect the heat exchanger coil 2 Ensure that the primary supply condensate water return line feed...

Страница 36: ...uired final torque loading all bolts at each step before proceeding to the next step e Use rotational tightening until all bolts are stable at final torque level A minimum of two 2 rotations is usuall...

Страница 37: ...Primary Supply Replacement Fig 19 If the pressure gauge for the energy source does not function correctly and must be replaced follow the procedures outlined below The combination of electricity steam...

Страница 38: ...can differ between units Refere to the drawing supplied with the unit to identify the location of the traps on the unit 3 Carefully break the joint on the inlet side and drain condensate line of the...

Страница 39: ...Reference the drawing supplied with the unit to identify the location of the strainers on the unit 3 Carefully break the line connections on the inlet and outlet side of both strainers 4 Remove and ex...

Страница 40: ...on operation and maintenance procedures The combination of electricity steam and water can pose a very dangerous situation Turn off disconnect all electric power before attempting any maintenance proc...

Страница 41: ...rained and that all components and surfaces have cooled 3 Carefully Disconnect the wires leading from to the control cabinet 4 Loosening the connections until the pressure probe can be removed 5 Exami...

Страница 42: ...er before attempting any maintenance procedure 1 Follow the shutdown procedure to take the unit off line before attempting to replace the steam pressure transmitter 2 Ensure that the primary supply co...

Страница 43: ...s documentation local codes or accepted contractor practices as to the use of joint compound or sealer at the connections 5 Reconnect the vent line leading from the pressure safety valve to atmospher...

Страница 44: ...res The combination of electricity steam and water can pose a very dangerous situation Turn off disconnect all electric power before attempting any maintenance procedures 1 Follow the shutdown procedu...

Страница 45: ...the pump must be removed for inspection adjustment or replacement follow the steps detailed below Clean steam and primary source steam or superheated water present situations that can be very dangerou...

Страница 46: ...orrect positioning For the exact procedure for examination refer to the Spirax Sarco manual information included with the unit 8 To install a new pump align with the feed lines and start the fittings...

Страница 47: ...t the valve 2 Ensure that the primary supply condensate water return line feed water inlet and clean steam outlet have been shut off that the pressure has been bled from both the steam and primary sup...

Страница 48: ...ation Turn off disconnect all electric power before attempting any maintenance procedures The PN9000 series pneumatic actuators and variants are maintenance free To ensure satisfactory operation it is...

Страница 49: ...ections and flange bolts for tightness With valves having high temperature graphite packed gland seals the gland nut should be tightened by approximately of a turn taking care not to over tighten as t...

Страница 50: ...l electric power before attempting any maintenance procedures Maintenance document ref IM P343 16 In normal working conditions bleed the air filter regulator on the supply air line daily by holding th...

Страница 51: ...oning and it is not possible to identify the fault the unit must be replaced To replace the unit please follow the procedure outlined below Note The exact location and configuration of the solenoid sa...

Страница 52: ...spect steam inlet control valve Replace all seals and refit with new gaskets Check operation of EP5 Remove strip and inspect bottom blow down control valve Replace all seals and refit with new gaskets...

Страница 53: ...ng the replaceable parts for the unit refer to the original design specifications or contact Spirax Sarco Please have the unit s model and serial number available when contacting Spirax Sarco Replacea...

Страница 54: ...210 50 Appendix A Sequential Order 1 2 3 4 5 6 7 8 Rotational Order 1 5 3 7 2 6 4 8 Sequential Order 1 2 3 4 5 6 7 8 9 10 11 12 Rotational Order 1 5 9 3 7 11 2 6 10 4 8 12 8 bolts 12 bolts Bolt Torque...

Страница 55: ...10 11 12 13 14 15 16 Rotational Order 1 9 5 13 3 11 7 15 2 10 6 14 4 12 8 16 Sequential Order 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Rotational Order 1 13 5 17 9 3 15 7 19 11 2 14 6 18 10...

Страница 56: ...0362 49 17 1 Fax 0362 49 17 307 REPAIR Please contact our nearest Branch Office or Agent or directly Spirax Sarco S r l Via per Cinisello 18 20834 Nova Milanese MB ITALY Tel 39 362 82 22 LOSS OF GUAR...

Отзывы: