![solarwatt EasyIn 60M Series Скачать руководство пользователя страница 23](http://html1.mh-extra.com/html/solarwatt/easyin-60m-series/easyin-60m-series_installation-instructions-manual_1314118023.webp)
Subject to change | © 2019 SOLARWATT GmbH | AZ-TM-PMS-1339 | Rev 001 | Version: 12/2019
Page 23
The remaining length of the transverse seal can be laid in
the meantime on the last fitted module.
The transverse seal is to be measured in such a way that it
extends over several modules. The transitions from mod
-
ule to module are each supported by using a transverse
seal clip (see Figure 25 and Figure 26).
Figure 24
Figure 25
Small notch to secure the
position of the transverse seal
clip to the left and right mod-
ule field side.
24mm
Transverse seal clip
between two modules
If a transverse seal (approx. 6.4 m) is not long enough
within a module row, then it is to be shortened near its
end so that the transition from one transverse seal to the
next can be made in one of the two clamp areas per mod-
ule each with two clamping lugs.
Figure 26
Figure 27