DIP Switch Setup
Termination and bias guidelines:
l
The last battery in the chain should have termination and bias
l
The last meter should have termination, without bias
l
Inverter communication board should not have termination if meter is installed, otherwise ON.
Verify that the DIP switches of all the devices are set as described in the following table, according to the
components used in the system and their location:
System Component
Communication and Termination
Switches
Address Switches
Inverter communication board
(
Termination
:
o
If a meter is installed: SW7 Down -
No termination
o
If a meter is not installed: SW7 Up -
termination ON.
(see also
N/A
Batteries Type B (
)
Modbus protocol
:
l
Single battery or the battery is the
last in the chain:
o
S2, S6: Left
o
S1, S5: Down
o
S3, S4: UP
l
If the battery is not the last in the
chain:
o
S2, S6: Left
o
S1, S5: Down
o
S3, S4: Down
Battery address 1 (ID 24) - located
closest to the inverter
o
Switch 1: Right
o
Switch 2: Right
o
Switch 3: Right
Battery address 2 (ID 25)
o
Switch 1: Left
o
Switch 2: Right
o
Switch 3: Right
Batteries Type C, E (
Termination
:
o
If the battery is not the last in the
chain: Middle - No termination
o
Single battery or the battery is the
last in the chain: Bottom -
Termination (with bias)
Modbus protocol
:
o
Right (RS485)
Battery Address 1 (ID 24) - located
closest to the inverter
o
Switch 1: Right
o
Switch 2: Right
o
Switch 3: Right
Battery Address 2 (ID 25)
o
Switch 1: Left
o
Switch 2: Right
o
Switch 3: Right
Meter (
N/A
Meter 1 address:
o
Switch 1
: Up
o
Other: Down
Meter 2 address:
o
Switch 2
: Up
o
Other: Down
SolarEdge
StorEdge
-Single
Battery/High
Capacity
Installation
MAN-01-00283-
1.1
28
DIP Switch Setup