5. Disconnect the DC and AC wires from the inverter. Open the DC and AC wires ferrite beads and set
them aside.
6. Disconnect the cable connecting the inverter digital board to the StorEdge Connection Unit.
7. Unscrew the two conduit nuts in the inverter securing the StorEdge Connection Unit to the inverter.
8. Open the StorEdge Connection Unit cover and disconnect:
l
Backed-up loads panel wires, if connected
l
External meter, if connected
9. Release the bracket securing the StorEdge Connection Unit to the wall.
10. Carefully remove the StorEdge Connection Unit with its mounting bracket from the wall.
Installing a New StorEdge Connection Unit
1. Open the StorEdge Connection Unit cover.
2. Position the new StorEdge Connection Unit below the inverter and from the inside of the inverter
grab the AC and DC wires extending from the unit conduits, as shown below:
Figure 48: Inserting the AC and DC conduits
3. Attach the StorEdge Connection Unit with its bracket to the wall and slightly close the screws. Do not
over tighten.
4. Reconnect the cable from the inverter digital board to the StorEdge Connection Unit.
5. Reconnect all the external wires and ferrite beads.
6. Securely screw the two conduit nuts onto the conduit ends in the inverter. Verify proper conduit
sealing.
7. Close the StorEdge Connection Unit cover. Attach the cover and secure it by tightening the six screws
with a torque of 1.2 N*m / 0.9 ft.*lb.
Appendix C: Replacing and Adding System Components
SolarEdge
-
StorEdge
-Single
Battery/High
Capacity
Installation
MAN-01-00283-1.
1
101