Commissioning
11.2 Check before powering on for the first time
Automation system
224
System Manual, 12/2017, A5E03461182-AE
Module installation and wiring
●
Are all the modules inserted / installed in accordance with the mounting plan and
corresponding to the configuration with STEP 7 and screwed firmly to the mounting rail?
●
Are all the front connectors wired according to the circuit diagram, in the final position,
and inserted on the correct module?
●
Are the correct modules installed and connected to each other with U connectors?
●
Are U connectors projecting either at the left-hand or right-hand over the outer modules
on the S7-1500 automation system/ET 200MP distributed I/O system?
System power supply or load current supply
●
Are all system power supplies and load current supplies switched off?
●
Is the power cable connector correctly wired?
●
Has the connection to line voltage been made?
Содержание Simatic S7-1500/ET 200MP
Страница 1: ......