Commissioning
5.2 Series Commissioning
Control Units CU240S
48
Operating Instructions, 07/2008 - FW 3.2, A5E00766042B AD
5.2
Series Commissioning
5.2.1
Common Information to Series commissioning
Description
Series commissioning means transferring the parameter set from one inverter into a number
of other inverters. This provides fast commissioning for identical applications, e. g. series
machines or group inverters.
Components for series commissioning
Commissioning the G120 inverter can be done in different ways. The following list provides
you an overview:
● Series commissioning with MMC
● Series commissioning with BOP
● Series commissioning with STARTER
For detailed information to series commissioning, refer to the chapters "Commissioning with
BOP", Commissioning with MMC", and "Commissioning with STARTER".
Order of series commissioning
The series commissioning is divided into the following steps:
● Creating a valid parameter set
● Uploading this parameter set
● Downloading of the uploaded parameter set into the next inverter
An appropriate parameter set can be created by parameterizing an inverter via BOP or
STARTER.
CAUTION
Parameter download between different types of Control Units and of different firmware
versions is not recommended.
It is possible to download parameter sets from different Control Unit types, however, as the
parameter sets might differ, the user is fully responsible for the consistency of the
downloaded parameter set.
Therefore, the customer has to confirm his responsibility in case of an automatic download
by acknowledging F0395.
During download of a parameter set from an MMC to the EEPROM of the Control Unit
CU240S (e.g. during serial commissioning) you have to note that the LEDs are flashing
correctly. If the Control Unit CU240S is in a fault state, the LEDs indicate this fault state
with higher priority than the download. It is not sure that the parameter set is downloaded
correctly.