Installation
Powerchain Systems
For systems with more than one SP PRO in a three-phase, split-phase or multi-inverter single-phase, the
following items should be verified. Please complete
For systems with only one SP PRO and
For systems with only one SP PRO and no external contactor:
page 38
IN0057 – Installation of an SP PRO Powerchain system
and ensure the system has been installed and commissioned according
to the document before completing the following checklist.
•
Turn on the DC supply to the SP PRO inverters (pre-charge and main DC breakers).
•
Turn on the AC Load circuit breakers connecting the workers to their managers.
•
Turn off the AC Source circuit breaker.
•
Connect SP LINK to System Manager (L1 Manager) via a USB lead to a Windows computer running
SP LINK.
•
Leave the inverters in idle.
Item to check
Result
Go to >
Powerchain Inverter Assignments
in SP LINK and check that all the inverters in the system
appear on the list.
Double click on each inverter serial number to ensure each inverter is in its correct position. The
associated inverter will flash its battery LEDs red.
Long press the ON button on System Manager (L1 Manager). Check that all the blue AC Load LEDs
and the green ON LEDs are lit and steady on all inverters.
In SP LINK click >
Data View
>
Now
>
L1 Manager
Place a Load on the system and check the Inverter AC Power.
Select each worker on L1 and check that each of their
Inverter AC Power is the same as their manager.
Repeat for L2 and L3 as appropriate.
Turn off the DC pre-charge and main DC battery supply to the SP PRO inverters.
Commissioning
Содержание SPPRO 2i Series
Страница 1: ......
Страница 2: ...Selectronic Australia 2023 ...
Страница 51: ...47 Selectronic Australia Rev 41 Dec 2022 Operation SP PRO Operation ...
Страница 64: ...Contents Doc O10003 Part 004122 Rev 41 Dec 2022 ...