SANY LATIN AMERICA
8-114
SY195/205/215/225C9 Crawler Hydraulic Excavator
Disassembly and Assembly
Shop Manual - June 2013
8.30.2 Installation
●
Installation is to be performed in the re-
verse order of removal.
Threads (mounting bolt - counter-
weight):
Thread adhesive (Tonsun 1277)
Mounting bolt (counterweight):
1,180~1,470 N·m {120~150 kgf·m}
Counterweight adjustment
1. Move the counterweight with a crane to a
suitable position on the frame.
2. Push the counterweight and install the
bolts. Adjust the position of the counter-
weight in such a manner that the following
dimensions can be obtained.
●
Clearance with swivel:
10±5 mm(L&R)
●
Clearance with bodywork door:
10±5 mm(L&R)
●
Step from swivel in left to right direction
b: max. 5 mm
●
Step from bodywork door in left to right
direction
a: 10±4
●
Step from bodywork top cover in upper
to lower direction
c: max. 5 mm
b=0±5mm
a=10±4mm
c=0±5mm
ZX215-1006205
Door
Counterweight
Swivel
https://www.tractormanualpdf.info/