9. Preparations for commissioning
98
© Sandvik SRP AB – Doc. no. S 223.510 en Ver. 1
CH420:01
9.1 General
Perform the following checks even if an actual commissioning test is not
required.
9.2 Presence and correctness checks
9.3 Supply value checks
NOTE!
Commissioning covers only the cone crusher itself. A line performance test
is still required to check the functioning of the cone crusher as part of a
production line. Contact the local service organization about arrangements
for a line performance test.
No.
Checks
Done
1
The data on the machine identification plate corresponds with
the machine specification document.
2
The ordered wear and spare parts have been delivered and
deposited in the spare part store.
3
All the documents correspond to the specific cone crusher:
- Operator’s manual
- Installation drawings
- Factory acceptance test report
- Machine specification document
- Machine deviation report (if relevant)
4
Sufficient process material is available for commissioning
purposes.
No.
Checks
Done
1
Hydroset and lubrication systems:
- Systems have been thoroughly cleaned
- Lubricants of the correct types are available
2
Electrical power supply:
- Voltage
- Max voltage fluctuation within limits
- Frequency
- Fuse rating
Содержание CH420:01
Страница 1: ...installation manual Doc no S 223 510 SANDVIK CH420 01 ...
Страница 8: ...Table of contents 6 Sandvik SRP AB Doc no S 223 510 en Ver 1 CH420 01 ...
Страница 19: ...1 Introduction 17 CH420 01 Sandvik SRP AB Doc no S 223 510 en Ver 1 This page is intentionally left blank ...
Страница 20: ...1 Introduction 18 Sandvik SRP AB Doc no S 223 510 en Ver 1 CH420 01 ...
Страница 31: ...29 Sandvik SRP AB Doc no S 223 510 en Ver 1 CH420 01 3 Technical data ...
Страница 42: ...3 Technical data 40 Sandvik SRP AB Doc no S 223 510 en Ver 1 CH420 01 This page is intentionally left blank ...
Страница 109: ......
Страница 110: ......