10    S&C Instruction Sheet 1045-510 

Installation

9.  Determine the value for the “RTN Time” setpoint.

Power must be restored to the faulted line segment for this amount of time (in 
minutes) before the Return to Normal process will start. Enter this information on the 

Setup—Restoration—IntelliTeam SG/II—Team X

 screen.

10.  Determine the Maximum Capacity for each team member.

The maximum capacity is the amount of load on the most limited line section
(because of conductor size, switch rating, etc.) served through a team member’s 
location from either direction. Each member continuously subtracts its present load 
from its 

Maximum Capacity

 to determine its 

Local Capacity for Transfer

. The small-

est 

Local Capacity for Transfer

 encountered in a particular restoration path deter-

mines the maximum load that the involved teams can transfer, the 

Available Capacity 

to Transfer

  You will enter this information in the 

Maximum Capacity

 setpoint on the 

Setup—

Restoration—IntelliTeam SG/II—Team X

 screen.

11.  Determine the alternate source sequence for each team.

Using the normal switch functionalities found in 

Step 7

, set the sequence in which 

team members will be used to restore the line segment. This is an optional step that 
can be used to guide the restoration process. Whether or not you have confi gured the 
alternate source sequence list, restoration will progress in the following order. If the 
fault is downstream of the team, the coach will: 1) try the normal source switch, 2) use 
the Alternate Source Sequence (if applicable), 3) try any Tie switch(es), and 4) try any 
Load-Tie switch(es). If the fault is upstream of the team, the coach will: 1) use the 
Alternate Source Sequence (if applicable), 2) try any Tie switch(es), 3) try any 
Load-Tie switch(es), and 4) try the normal source switch. Enter this information in
the 

Alternate Source Sequence

 setpoints on the 

Setup—Restoration—IntelliTeam 

SG/II—Team X

 screen.

12.

 

Determine whether any “contracts” are required to avoid overloading a line 

segment.

A bifurcated circuit acting as an alternate source for teams on both legs of the bifurca-
tion may become overloaded if those teams must act to restore load at close to, or 
exactly, the same time. This overload may occur because those teams are not directly 
related, and do not coordinate their reconfi guration activities.

  To force the coordination between these unrelated teams you should set the 

Contract Required

 setpoint to 

Yes

 on the 

Setup—Restoration—IntelliTeam SG/II—

Team X

 screen for teams that may add load to the alternate circuit during a reconfi gu-

ration event. The contract will prevent both teams from simultaneously closing to use 
the alternate source. When team members encounter a line segment in a restoration 
path that requires a contract, they will communicate with all subsequent line 
segments in the direction of the alternate source to ensure that the source and line 
segments will not be overloaded. The fi rst team contract to arrive at the source would 
be approved if the team load would not overload the circuit. The second arriving con-
tract would be approved only if it would also not cause an overload.

  The extra communication required to transmit the contracts slows down the recon-
fi guration process. Contracts are described in S&C Instruction Sheet 1045-540: 

Loading Restrictions

 on page 26 and 

Contracts

 on page 27.

13.  Determine whether you need to limit the number of line segments restored 

by a team.

If you want to limit the number of line segments that a team picks up, you will need to 
enable the 

Line Segment Limit

 setpoint, on the 

Setup—Restoration—IntelliTeam 

Содержание 6800 Series

Страница 1: ...1 GPS Option 14 WiFi Option 15 Communication Connections 17 Optional In Shop Setup 17 Installation Steps 18 Install the Enclosure and Connect Wiring 18 Connect the Battery 22 Check Input Connections 2...

Страница 2: ...f said warranty is replaced by the following 1 General Seller warrants to immediate purchaser or end user for a period of 10 years from the date of shipment that the equipment delivered will be of the...

Страница 3: ...injury or product or property damage if instructions including recommended precautions are not followed NOTICE NOTICE identifies important procedures or requirements that can result in product or prop...

Страница 4: ...all locally approved safety procedures when working on or around this switch control Before attempting to access an existing switch installation check carefully for visible or audible signs of electr...

Страница 5: ...cluding this switch control NOTICE These flowcharts assume that the team consists entirely of S C 6800 Series Switch Controls If your team includes other types of controls or IntelliRupter PulseCloser...

Страница 6: ...Phase 2 Team Installation Setup Phase 2 Go to Phase 3 see next page Start here after you have completed Phase 1 Program all DNP radios in the shop Make sure all radios communicate Go to the site of th...

Страница 7: ...S C Instruction Sheet 1045 510 7 Installation Figure 3 Suggested Team Setup Phase 3 Team Installation Setup Phase 3 Start here after you have completed Phase 2...

Страница 8: ...eam designations for Team 1 to Team 8 as needed for the Setup Restoration IntelliTeam SG II Team X screens Teams that share a team member must have different designations 4 Assign each team member a D...

Страница 9: ...when the switch would not be involved when restoring power to the line segment because the other line segments have no alternate sources Open Switches Tie Sub Use this value when the tie switch is the...

Страница 10: ...Tie switch es 3 try any Load Tie switch es and 4 try the normal source switch Enter this information in the Alternate Source Sequence setpoints on the Setup Restoration IntelliTeam SG II Team X screen...

Страница 11: ...sandc com An onboard Ethernet card is required for IntelliTeam Designer Software Serial or USB Cable Connects the computer to the DATA PORT on the control Use a straight through cable not a null mode...

Страница 12: ...or your type of distribution system 3 Wires Grounding Type Use Uni grounded Wye System Delta jumper s 4 Wires Grounding Type Use Uni grounded Wye System Primary Neutral Delta jumper s Multi grounded W...

Страница 13: ...losure interior 6 Check the battery A 6800 Series Switch Control is shipped with either a Hawker Gates Monoblock 24 Vdc or 36 Vdc battery The battery is terminated with a connector that can be connect...

Страница 14: ...pin 24 pin cable adapter available from S C This is only necessary for early Scada Mate Switches GPS Option The optional GPS board is mounted on the display side of the processor board and covered by...

Страница 15: ...d enclosure the WiFi antenna is mounted on the bottom and for pad mounted gear a dual GPS WiFi antenna is installed on the top of the low voltage enclosure See Figure 11 on page 16 The WiFi transceive...

Страница 16: ...right on this pad mounted gear enclosure Figure 12 The WiFi transceiver connects to the Serial port on the control panel Figure 13 Connections to the WiFi transceiver board other jacks are not used P...

Страница 17: ...figuration instructions see the manufacturer s documentation or contact S C 4 If a repeater radio is needed to link this switch control to the other team members configure the repeater radio For radio...

Страница 18: ...as already been integrated into pad mounted equipment and the switch control is powered from the sensors only skip the remainder of this chapter and go directly to S C Instruction Sheet 1045 530 For a...

Страница 19: ...nd associated mounting hardware as if they were elevated to primary high voltage You must follow the sequence of installation steps outlined in this chapter to ensure a safe and successful switch cont...

Страница 20: ...low voltage compartment as follows 1 Find the four studs on the wall of the low voltage compartment 2 Position the switch control so that the four studs align with the four holes in the mounting flan...

Страница 21: ...communication and may optionally communicate with SCADA You must toggle the faceplate SCADA CONTROL switch to LOCAL to ensure that the switch control does not carry out remote switching commands until...

Страница 22: ...battery was shipped separately install it now WARNING If the enclosure heater was recently on the battery bracket may be hot Be careful not to touch a hot bracket The battery bracket is near the high...

Страница 23: ...he clip on the battery bracket 2 Connect the battery With the AC Line Fuse still removed connect the red and black battery leads to the corresponding leads from the switch control This will supply dc...

Страница 24: ...uts at J2 and J4 See Figure 22 For installations using three voltage sensors and nine current sensors the voltage input should be connected at J3 and the current inputs at J2 J4 and J6 See Figure 22 C...

Страница 25: ...G ON LEDs When you insert the 10 A AC Line fuse the red AC ON and CHG ON LEDs should illuminate See Figure 21 on page 23 If the AC ON and CHG ON LEDs do not illuminate check the external ac voltage so...

Страница 26: ...o OFF see S C Instruction Sheet 1045 550 d Check that the LCD is backlit and that data is displayed Then press the PREV and NEXT and buttons to make sure that the display will scroll in all four direc...

Страница 27: ...ellow Sensor Calibration sheet that came with the switch There will be a sheet for each set of sensors Put a copy in the door pocket of the control or low voltage cabinet The Sensor Calibration sheet...

Страница 28: ...ications equipment has power For overhead switch controls the communications equipment is on the back of the faceplate For 6800 Series Switch Controls installed in pad mounted gear the communication e...

Страница 29: ...S C Instruction Sheet 1045 510 29 Installation Diagrams...

Страница 30: ...30 S C Instruction Sheet 1045 510 Installation Diagrams...

Страница 31: ...S C Instruction Sheet 1045 510 31 Installation Diagrams...

Страница 32: ...32 S C Instruction Sheet 1045 510 Installation Diagrams...

Страница 33: ...S C Instruction Sheet 1045 510 33 Installation Diagrams...

Страница 34: ...34 S C Instruction Sheet 1045 510 Installation Diagrams...

Страница 35: ...S C Instruction Sheet 1045 510 35 Installation Diagrams...

Страница 36: ...36 S C Instruction Sheet 1045 510 Installation Diagrams...

Страница 37: ...S C Instruction Sheet 1045 510 37 Installation Diagrams...

Страница 38: ...38 S C Instruction Sheet 1045 510 Installation Diagrams...

Страница 39: ...S C Instruction Sheet 1045 510 39 Installation Diagrams...

Страница 40: ...40 S C Instruction Sheet 1045 510 Printed in U S A Installation Diagrams...

Отзывы: