LIFT MODEL VISION AS 300 Rev001
7-5
7.7
Assembly
1. Preparing the concrete surface in position of the landing door. Verify that the distance of
the base frame from the structure is compatible to the landing door. The machine must
be installed on a bearing platform made in concrete with two steel net of reinforcement
able to bear the load from the base frame. The M20 bolts must be cast into the concrete.
2. Once the base frame has been positioned on the ground, insert the vertical element in
the special seats and lock it with M12 screws. Make sure that the mast locking bolts
and nuts
at the base are tightened. In the opposite
case tighten them properly. Then fix
the junction box to the vertical element.
44. Mount another two vertical elements and lock them with the screws.
45. Insertion of the cabin group. Raise the motor group along the trestle previously mounted.
Verify that the hoisting gears are in phase with the rack teeth. To that extent the
parachute emergency brake must be open. Also release necessarily the electromagnetic
brakes of the motors through the special knob.
46. Connect the power supply cable to the electric panel, after fasten the cable to the cable
holder arm on the motor drive and make sure that there is at least 0.5m of cable which is
left for any possible adjustment.
47. Connect the other end of the electrical cable on the junction box and make sure the
cables are not going to interfere with the moving parts. Subsequently connect the
junction box to the electricity net.
48. Remove the wheel cable guide and two roller of the trolley.
49. Fit the trolley in the mast, then remount the two roller to fix the frame to the column.
50. Insert the wheel into the housing, making sure that the cable runs as in picture.
Содержание VISION AS 300
Страница 2: ......
Страница 4: ......
Страница 43: ...LIFT MODEL VISION AS 300 Rev001 7 4 Fig 7 1 Dimension...
Страница 68: ...LIFT MODEL VISION AS 300 Rev001 12 1 12 WIRING DIAGRAMS Fig 12 1 Wiring diagram Power supply...
Страница 69: ...LIFT MODEL VISION AS 300 Rev001 12 1 Fig 12 2 Wiring diagram Motor power supply...
Страница 70: ...LIFT MODEL VISION AS 300 Rev001 12 2 Fig 12 3 Wiring diagram Emergency circuit...
Страница 71: ...LIFT MODEL VISION AS 300 Rev001 12 3 Fig 12 4 Wiring diagram Auxiliary...
Страница 72: ...LIFT MODEL VISION AS 300 Rev001 12 4 Fig 12 5 4 Wiring diagram Auxiliary PLC logo expans...
Страница 73: ...LIFT MODEL VISION AS 300 Rev001 12 5 Fig 12 6 Auxiliary circuit...
Страница 74: ...LIFT MODEL VISION AS 300 Rev001 12 6 Fig 12 7 Wiring diagram Connectors C1 C2 C3...
Страница 75: ...LIFT MODEL VISION AS 300 Rev001 12 7 Fig 12 8 Wiring diagram Terminal box electric panel...
Страница 76: ...LIFT MODEL VISION AS 300 Rev001 12 8 Fig 12 9 Wiring diagram Cable call floor...
Страница 77: ...LIFT MODEL VISION AS 300 Rev001 12 9 Fig 12 10 Wiring diagram Floors call connection...
Страница 78: ...LIFT MODEL VISION AS 300 Rev001 12 10 Fig 12 11 Wiring diagram Box floor call connection...
Страница 79: ...LIFT MODEL VISION AS 300 Rev001 12 11 Fig 12 12 Wiring diagram Box Fencing connection...
Страница 80: ...LIFT MODEL VISION AS 300 Rev001 12 12 Fig 12 13 Wiring diagram Cable fancing call...
Страница 81: ...LIFT MODEL VISION AS 300 Rev001 12 13 Fig 12 14 Main electrical box components...
Страница 82: ...LIFT MODEL VISION AS 300 Rev001 12 14 Fig 12 15 Material list 1...
Страница 83: ...LIFT MODEL VISION AS 300 Rev001 12 15 Fig 12 16 Material list 2...