installation
Diagram 4
6.
The arrow on the vent cap should
be pointing up.
Insure that the 1-1/2"
clearances to combustible materials
are maintained (Diagram 4.. Install the
termination cap.
NOTE: For Snorkel terminations in ABOVE
grade installations, follow national
or local code requirements.
Below Grade Installation
If the Snorkel Termination must be installed
below grade, i.e. basement application, proper
drainage must be provided to prevent water
from entering the Snorkel Termination. Refer
to Diagram 4. Do not attempt to enclose the
Snorkel within the wall, or any other type of
enclosure.
*Dia 3, 3a & 4: As specified in CGA B149
Installation Code. Local codes or regulations
may require different clearances.
Diagram 1
b)
Horizontal runs of vent must be
supported every three feet. Wall straps
are available for this purpose.
5.
Mark the wall for a 10" x 10" square hole.
The center of the square hole should line
up with the centerline of the horizontal pipe.
Cut and frame the 10 inch square hole in
the exterior wall where the vent will be
terminated. If the wall being penetrated is
constructed of non-combustible material,
i.e. masonry block or concrete, a 7"(178mm)
dia. (7-1/2"(191mm) dia. for flex) hole is
acceptable.
Diagram 2
Note:
a)
The horizontal run of vent must be level,
or have a 1/4 inch rise for every 1 foot
of run towards the termination. Never
allow the vent to run downward. This
could cause high temperatures and may
present the possibility of a fire.
b)
The location of the horizontal vent termi-
nation on an exterior wall must meet all
local and national building codes, and
must not be blocked or obstructed. For
External Vent Terminal Locations, see
diagram in the "Exterior Vent Termination
Locations" section.
c)
Snorkel Terminations:
For installations requiring a vertical
rise on the exterior of the building, 14-
inch and 36-inch tall
Snorkel Terminations
are available, as
well as the standard
Riser Vent. Follow the
same installation
procedures
as used for
standard
Horizontal
Termination.
N E V E R
install the
s n o r k e l
u p s i d e
down.
Diagram 3
Diagram 3a
Note: Riser Vent
is only for use
in above grade
terminations.
NOTE:
For best results and optimum perfor-
mance with each approved venting system,
it is highly recommended to apply “Mill-
Pac” sealant (supplied) to every inner pipe
connection. Failure to do so may result in
drafting or performance issues not covered
under warranty.
Note: With
DuraVent,
the
minimum
height is
achieved by
installing a
90
o
elbow
directly to
the top of
the unit.
HORIZONTAL
TERMINATIONS
Install the vent system according to the
manufacturer's instructions included with
the components.
1.
Set the unit in its desired location. Check
to determine if wall studs or roof rafters
are in the way when the venting system is
attached. If this is the case, you may want
to adjust the location of the unit. Rough in
the gas preferably on the right side of the
unit and the electrical (junction block is on
the left side) on the left.
2.
Direct Vent pipe and fittings are designed with
special twist-lock connections to connect the
venting system to the appliance flue outlet. A
twist-lock appliance adaptor is an available
option that must be used in conjunction with
the Simpson Dura-Vent Direct Vent system.
3.
Put a bead of silicone inside the outer section
of the adapter and a bead of Mill Pac on
the inner collar. Slip the adapter over the
existing inner and outer flue collar and fasten
to the outer collar only with the 3 supplied
screws (drilling pilot holes will make this
easier). Level the fireplace and fasten it to
the framing using nails or screws through
the nailing strips.
4.
Assemble the desired combination of pipe
and elbows to the appliance adaptor and
twist-lock for a solid connection.
Note:
a) Twist-lock procedure: Four indentations,
located on the female ends of pipes and
fittings, are designed to slide straight
onto the male ends of adjacent pipes
and fittings, by orienting the four pipe
indentations so they match and slide
in to the four entry slots on the male
ends, Diagram 1. Push the pipe sections
completely together, then twist-lock
one section clockwise approximately
one-quarter turn, until the two sections
are fully locked. The female locking lugs
will not be visible from the outside, on
the Black Pipe or fittings. They may be
located by examining the inside of the
female ends.