50
>>
STRUCTURE
CAUTION
w
Once the
structure has
been assembled,
make sure that the
diagonals are equal
in length.
w
Check that the
posts are level and
straight.
w
Check that the
height is correct.
Diagram:
A corresponds to a fl at bar with an interaxial distance of 1m.
B corresponds to a fl at bar with an interaxial distance of 1.5m
C corresponds to a fl at bar for top corners
At the bottom corners, these fl at bars are joined together by an AR type jack
(Detail fi g.6)
Figure 8b
Figure 8c
Figure 8a
POOL
3X6
POOL
4X8
POOL
5X10
w
Lay the top layer of rebar (second layer) over the entire surface of the excavation
before pouring the concrete.
w
Once laid, the metal trellis should cover the whole surface (lay the trellis such that it is
set 3 to 5 cm back from the edge around the entire periphery). Some cutting around
the posts will be necessary (fi g 9a.). Bars should be allowed to overlap and should be
connected together.
»
INSTALLATION INSTRUCTION
/ RECTANGLE