QUICK OVERVIEW
>> Excavation
>> Assembly of the metal structure
>> Pouring the concrete slab
>> The wooden structure
>> The fi ltration group
Tools :
(excluding concrete works and excavation)
a decameter, a rope, tube wrench (13 and 17), a mallet, a screw gun (with
a torx, pozi bit), a Stanley knife, a metal saw, a big spirit level, a fl at head
screw driver, a cross head screw driver, bolt cutters, sand paper, a fi le,
excavation equipment.
Time required :
w
Excavation:
1 to 2 days (depending on the materials used)
w
Metallic structure
1 day (with 2 people)
w
Pouring the slab:
1 to 2 days (with 2 people and depending on the materials used)
w
Wooden structure and fi ltration :
2 to 3 days (with 2 people). The time indicated does not include the
concrete curing time.
w
Curing of the concrete slab before fi lling the pool with water : 2 to 3
weeks