ELECTRICAL
10.22
CURRENT DRAW - KEY OFF
CAUTION: Do not connect or disconnect the battery
cable or ammeter with the engine running. Damage
will occur to light bulbs and speed limiter.
Connect an ammeter in series with the negative
battery cable. Check for current draw with the key off.
If
the
draw
is
excessive,
loads
should
be
disconnected from the system one by one until the
draw is eliminated. Check component wiring as well
as the component for partial shorts to ground to
eliminate the draw.
Current Draw - Key Off:
Maximum of .01 DCA (10 mA)
CHARGING SYSTEM “BREAK
EVEN” TEST
CAUTION:
Do not allow the battery cable or
ammeter to become disconnected with the
engine running. Follow the steps below as
outlined to reduce the chance of damage to
electrical components.
WARNING:
Never start the engine with the ammeter
connected in series. Damage to the meter or meter
fuse will result. Do not run test for extended period of
time. Do not run test with high amperage accessories.
The “break even” point of the charging system is the
point at which the alternator overcomes all system
loads (lights, etc.) and begins to charge the battery.
Depending on battery condition and system load, the
break even point may vary slightly. The battery should
be fully charged before performing this test.
1.
Connect
a
tachometer
according
to
manufacturer’s instructions.
2.
With the negative cable still connected to the
battery, connect one meter lead (set to DC amps)
to the battery post and the other to the negative
battery cable
3.
With engine off and the key and kill switch in the
ON position, the ammeter should read negative
amps (battery discharge). Reverse meter leads if
a positive reading is indicated.
4.
Shift transmission into neutral and start the
engine.
With the engine running at idle,
disconnect the negative cable from the battery
post without disturbing the meter leads. Observe
meter readings
5.
Increase engine RPM while observing ammeter
and tachometer.
6.
Note RPM at which the battery starts to charge
(ammeter indication is positive).
7.
With lights and other electrical load off, the “break
even” point should occur at approximately 1500
RPM or lower.
8.
Turn the lights on and engage parking brake lock
to keep brake light on.
9.
Repeat test, observing ammeter and tachometer.
With lights on, charging should occur at or below
2000 RPM.
ALTERNATOR OUTPUT TEST
(AC AMP)
This test measures AC amperage from the alternator.
CAUTION: This test simulates a “full load” on the
alternator at idle. Do not increase idle RPM or perform
this test longer than required to obtain a reading. The
alternator stator windings may overheat.
3--5
seconds is acceptable.
To Calculate Available Alternator Output
250W
12V
=
20.8 Amps
I
=
P
E
I = Current in Amps
P = Power in Watts
E = Electromotive Force (Volts)
200W
12V
=
16.7 Amps
1.
Maximum alternator output will be indicated on
the meter. DO NOT increase engine RPM above
idle.
2.
Place the red lead on the tester in the 10A jack.
3.
Turn the selector dial to the AC amps position.
4.
Connect the meter leads to the Yellow and
Yellow/Red wires leading from the alternator.
5.
Start the engine and let it idle. Reading should be
a minimum of 5A/AC at idle.
Alternator Current Output:
Minimum of 5 AC Amps at Idle
Содержание A09BA50FA
Страница 63: ...ENGINE 3 13 EH50PL ENGINE EXPLODED VIEW Crankcase Cylinder Cylinder Head Crankshaft and Piston Valve Train A...
Страница 70: ...ENGINE 3 20 CYLINDER HEAD EXPLODED VIEW EH50PL EH50PL...
Страница 120: ...FUEL SYSTEM CARBURETION 4 16 NOTES...
Страница 216: ...BRAKES 9 24 NOTES...
Страница 254: ...ELECTRICAL 10 38 NOTES...
Страница 255: ...ELECTRICAL WIRING DIAGRAM 2009 SCRAMBLER 500...
Страница 256: ...ELECTRICAL WIRING DIAGRAM 2009 SCRAMBLER 500...