INSTALLATION
II.1
PREPARATION
II.1.1 EQUIPMENT RECEPTION
II.1.1.1 Equipment delivered:
The following are delivered with the CCR:
▪
The “Installation and Maintenance” instructions manual for the device
▪
Factory test report for the device
II.1.1.2 Checking the equipment:
When the device is received, check that the frame and its components (in particular the electronic and
LV units) are in good mechanical condition with no distortion or signs of impact.
Check also that the power transformer shows no signs of being transported in a wrong position and that
its protective packaging is not damaged.
II.1.2 TRANSPORTATION
Stand alone CCR :
The CCR can be moved and transported using its rollers and the two removable lifting rings
Stacked CCR
Don’t use the 2 small lifting rings shown above, but only the 4 long lifting rails
shown below :
Содержание AUGIER energy DIAM3100 Series
Страница 2: ...DIAM3100 2012 AUGIER SA I 2...
Страница 6: ...DIAM3100 2012 AUGIER SA I 6...
Страница 13: ...DIAM3100 2012 AUGIER SA I 13 I 2 4 DIMENSIONS...
Страница 14: ...DIAM3100 2012 AUGIER SA I 14 Stacked CCRs...
Страница 28: ...DIAM3100 2012 AUGIER SA I 28...
Страница 56: ...DIAM3100 2012 AUGIER SA V 56 V APPENDIX A DIAGRAM...