36
Installation
2582302_C_EN_1611
Nortec EL
5.6
Water Connections
Refer to
"Site Requirements" on page 15
for the water supply and drain requirements.
Read
"Water Connection Requirements" on page 38
, and perform the water connections as shown in
Figure 21
on page 36
and
Figure 22 on page 37
.
5.6.1 Water Connections Overview
Figure 21:
8
10
11
5
7
6
4
2
1
3
5
4
9
Water Supply and Drain Connections, Small and Medium Units
1 Drain canal (outlet un-threaded), 1-3/16 in (30 mm) O.D.
2 Hose clamp (supplied)
3 Flexible bent hose (supplied)
4 Drain line, minimum 7/8 in (22 mm) I.D. (not supplied)
5 Water supply line, minimum 1/2 in (13 mm) (not supplied)
6 Adaptor, 3/4 BSPP to 1/2 in NPT (supplied)
7 Fill valve (3/4 in BSPP plastic threads)
8 Air gap and optional trap (not supplied)
9 Shutoff valve (not supplied)
10
Filter, 5 μm (optional, but recommended)
11
Union fitting (not supplied)