Pre-Energization Checks
43
MV Termination Verification
On both the Utility Side and Solar Side, all six (6) MV elbows should be be fully seated
on the inserts.
200A load-break connections are pushed on until the are fully seated and no “color ring”
is visible.
600A dead-break connections (e.g. “T-bodies”) are bolted on and need to be fully
seated and torqued per manufacturer instructions.
Содержание ClearSky
Страница 1: ...myPV ClearSky User Manual 1 myPV ClearSky User Manual ...
Страница 12: ...Resources 12 ...
Страница 14: ...Resources 14 ...
Страница 19: ...Resources 19 ...
Страница 20: ...Resources 20 ...
Страница 48: ...Pre Energization Checks 48 Control Panel Verification Locations ...
Страница 55: ...Initial Energization 55 ...
Страница 63: ...Operational Testing 63 The myPV ClearSky may be left in this condition indefinitely ...
Страница 64: ...Operational Testing 64 Numbered Illustration of Mode Selection Switch Protective Relay Indicators ...
Страница 68: ...Spare Parts 68 ...
Страница 69: ...Spare Parts 69 ...