Initial Energization
57
Fused PT References Shown OPEN, for Voltage Testing
With all three (3) fused PT references closed, the following verifications may be made
using the SEL-735 Meter and SEL-751 Protection Relay:
L-L interconnection voltages
If L-L (or L-N) voltages are not within the expected interconnection ranges,
verify the PTR and CTR settings in the SEL-735 Meter and SEL-751 Protection
Relay
Frequency
Phase Rotation
For information regarding operation of the SEL-735 or SEL-751 for the purposes of the
verifications above, please reference to the SEL Instruction Manuals ay
https://www.selinc.com, or give us a call.
Please continue to the next section, Operational Testing, for relay operation (CLOSEing-
In)
Содержание ClearSky
Страница 1: ...myPV ClearSky User Manual 1 myPV ClearSky User Manual ...
Страница 12: ...Resources 12 ...
Страница 14: ...Resources 14 ...
Страница 19: ...Resources 19 ...
Страница 20: ...Resources 20 ...
Страница 48: ...Pre Energization Checks 48 Control Panel Verification Locations ...
Страница 55: ...Initial Energization 55 ...
Страница 63: ...Operational Testing 63 The myPV ClearSky may be left in this condition indefinitely ...
Страница 64: ...Operational Testing 64 Numbered Illustration of Mode Selection Switch Protective Relay Indicators ...
Страница 68: ...Spare Parts 68 ...
Страница 69: ...Spare Parts 69 ...