5.0
ProStar MPPT Operator’s Manual
59
Operation
58
Schedule
Maintenance Items
2 weeks after installation
Re-tighten power terminal
connections to specified
torque values.
3 months after installation
Re-tighten power terminal
connections to specified
torque values.
Monthly or After Each
Equalization
Inspect the battery bank.
Look for cracked or
bulging cases, and corroded
terminals.
For wet cell (flooded type)
batteries, make sure the
water level is correct. Wet
cell water levels should be
checked monthly or accord-
ing to the manufacturer’s
recommendations.
Annually
Clean the heatsink fins with a
clean, dry rag.
Inspect all wiring for
damage or fraying.
Inspect for nesting insects.
Re-tighten all wiring terminal
connections to specified
torque values.
Inspect the system earth
grounding for all compo-
nents. Verify all grounding
conductors are appropriately
secured to earth ground.
Table 4-6. Maintenance Schedule
WARNING:
RISK OF ELECTRICAL SHOCK.
NO POWER OR ACCESSORY TERMINALS ARE ELEC-
TRICALLY ISOLATED FROM DC INPUT, AND MAY BE ENER-
GIZED WITH HAZARDOUS SOLAR VOLTAGE. UNDER CERTAIN
FAULT CONDITIONS, BATTERY COULD BECOME OVER-
CHARGED. TEST BETWEEN ALL TERMINALS AND GROUND
BEFORE TOUCHING.
AVERTISSEMENT:
RISQUE DE CHOC ÉLECTRIQUE.
NON ALIMENTATION OU AUX BORNES
D'ACCESSOIRES SONT ISOLÉS ÉLECTRIQUEMENT DE
L'ENTRÉE DE C.C ET DOIT ÊTRE ALIMENTÉS À UNE TENSION
DANGEREUSE SOLAIRE. SOUS CERTAINES CONDITIONS DE
DÉFAILLANCE, LA BATTERIE POURRAIT DEVENIR TROP CHAR-
GÉE. TEST ENTRE TOUTES LES BORNES ET LA MASSE AVANT
DE TOUCHER.
WARNING:
Shock Hazard
A means of disconnecting all power supply poles must
be provided. These disconnects must be incorporated
in the fixed wiring. Open all power source disconnects before
removing controller wiring cover, or accessing wiring.
AVERTISSEMENT:
Risque de décharge électrique
Un moyen de déconnexion de tous les poteaux
d'alimentation doit être fourni. Ceux-ci se déconnecte doit
être intégrée dans le câblage fixe. Ouvrir que toutes les source
d'énergie se déconnecte avant de retirer le couvercle de la
contrôleur, ou accès au câblage.
5.1 LED Fault Indications
Load Over-current
Error Status LED: Flashing red. Battery status LEDs: R/Y-
G sequencing. If the load current exceeds the maximum
load current rating, the ProStar MPPT will disconnect the
load. The greater the overload the faster the load will be
5.0 TROUBLESHOOTING