Page 3-3
Chapter 3: Changing Heating Systems
|
Section 3.2: Changing from Hot Wedge to Hot Air
Section 3.2: Changing from Hot
Wedge to Hot Air
1.
Turn the Heat and Power Switch to the off
position to activate the cool down cycle and
wait for the machine to shut down.
2.
Once the cool down cycle is complete and the
machine has shut down the Main Power Supply
must be disconnected. To do this turn off the
Circuit Breaker to the off position.
(Figure3.15)
3.
The Main Air Supply must also be
disconnected and depressurized. First,
disconnect the Shop Air Supply by turning the
ball valve to the off position. Second, release
the quick connect fitting on the end of the air
line which will allow you to remove it. Third,
bleed off the remaining air in the system by
slowly turning the ball valve to the on
position. Once all the remaining air has
escaped and the air cylinders are relaxed turn
the ball valve back to the off position.
(Figure3.16)
4.
Once the wedge has sufficiently cooled down
and the Main Power an Air Supply have been
disconnected remove the Fabric Guide from
the machine. This will help clear obstructions
while changing the Heating System.
5.
The Front Locking Bolt must be loosened
before changing the heating system. Use a
3/16” Allen Wrench to loosen the Front
Locking Bolt.
(Figure3.17)
6.
Disconnect the green airline that supplies the
Solenoids on the Hot Wedge Assembly by
pushing in on the white plug located at the
end of the y-fitting and pulling out the airline.
(Figure3.18)
7.
Loosen the screws on the two grey connectors
located on top of the machine and unplug
them.
(Figure3.19)