Assembly manual FS2 EI60/120 Version 11, jan.. 2021
-
For the indirect installation method, the gap between the shaft box and the guide rails and the wall and
the shaft box is to be filled with non-flammable material, e.g. class A1 mineral wool, min. density 170
kg/m3, which must cover the offset brackets.
13. Outdoor mounting curtain door outside of a shelter
If the curtain door is installed on the building exterior, outside of any shelter, a drip cap must be installed.
For the indirect installation method, secure the drip cap with door frame anchors, if the substrate
is reinforced concrete. Remove the building thermal insulation layer between the shaft box and the wall and
replace with fire-proof insulation.
1 Reinforced concrete wall
2 Installation anchor
3 Guide rail adjustable offset bracket
4 Self-drilling screw
5 Curtain running shoe
6 Curtain
7 Fire-rated insulation material
8 Building thermal insulation layer
9 Guide rail channel bar
10 M8 countersunk bolt with washer
and nut
11 M10 countersunk bolt with washer
and nut
Image Wall-mounted installation of the guide rail with fire-proof insulation
Indirect installation of the EI60 curtain door shaft box with a drip cap on the reinforced concrete
1 Reinforced concrete header
2 Shaft box drip cap
3 Shaft complete with the curtain
4 Installation anchors
5 Curtain counterweight
6 Offset bracket
7 Fire-rated insulation material
8 Building thermal insulation layer
,
− Dimensions per the installa on
conditions