Single-phase Testing—PPX30/30A Combined with Baker AWA Tester
When performing single-phase testing (for example , on DC motors or when testing single coils) you must use the
Temperature/Resistance Test
setup window to define the parameters that instruct the tester to operate in single-
phase testing mode.
NOTE: The parameters set in the Temperature/Resistance Test setup window affect only the Megohm and DA/PI tests
because the AWA test leads are used for these tests when used in combination with a PPX30/30A tester. The power
pack’s test leads are used, in turn, for DC HiPot and Surge testing, which are not controlled by the AWA’s setup
windows.
The Temperature/Resistance Test setup window is the only place where you specifically define parameters to enable
single-phase testing for the Baker AWA host unit.
1. Click on the test configuration button at the end of the second/Resistance row in the
Temperature/Resistance
Tests
section.
2. Click on the
Temperature Enable
radio button if you will be using temperature compensation.
3. Click on the
Resistance Enable
radio button to enable the parameter options in this area.
4. Click on
2 Leads (1 phase)
and check the
Res Leads
box. Notice that the list of leads to test in the
Test Results
section changes to include only one test lead set (Lead 1–2).
5. You can leave the
Resistance Enable
radio button active if you choose to run resistance tests, or turn it off if
not. However, you must ensure that the
2 Leads (1 phase)
radio button is selected and the
Res Leads
box is
checked to enable single-phase testing.
Fig 27:
Setting up the Resistance Test parameters for single-phase testing.
CAUTION: As noted above, the PPX30/30A test leads are used during DC HiPot and Surge testing, and they are not
controlled by the “2 leads” setting defined in the Temperature/Resistance Test setup window. The power pack’s test
leads should always be treated as energized leads when handling them.
Using Power Packs with Baker AWA Testers
www.megger.com 31
Содержание PPX30
Страница 1: ...Baker Power Packs PPX30 PPX30A PPX40 User Guide...
Страница 2: ......
Страница 6: ...Notices iv Baker Power Packs User Guide 71 061RC EN V2 www megger com...
Страница 12: ...Baker Power Pack Introduction 4 Baker Power Packs User Guide 71 061RC EN V2 www megger com...
Страница 24: ...Baker Power Pack Setup 16 Baker Power Packs User Guide 71 061RC EN V2 www megger com...
Страница 28: ...Using Power Packs with Baker AWA Testers 20 Baker Power Packs User Guide 71 061RC EN V2 www megger com...
Страница 74: ...66 Baker Power Packs User Guide 71 061RC EN V2 www megger com...
Страница 78: ...70 Baker Power Packs User Guide 71 061RC EN V2 www megger com...
Страница 82: ...74 Baker Power Packs User Guide 71 061RC EN V2 www megger com...