Transformer Testing
AVTMTO210 Rev 7 Sept 2013
31
Testing a Three-Phase Transformer
The following details the different methods to be used in testing three-phase
transformers. The measurements taken will be for one or two winding(s) at a
time. Connection diagrams (Figures 4 thru 7) are to be used in conjunction with
procedure "Single-Phase Transformer Test". The only changes will be placement
of leads.
NOTE: When testing Primary and Secondary windings simultaneously, always
try and keep the polarization of the transformer the same for improved
transformer charge time. See Table 1.
PROCEDURE:
1.
Three-Phase Wye Configured Winding with Neutral
Figure 4: Reading obtained is per phase, Resistance of A-N Winding
Use the above diagram in conjunction with procedure "Single-Phase
Transformer Test".
Содержание MTO210
Страница 2: ......
Страница 3: ...Transformer Ohmmeter DC Winding Resistance Test Set MTO210...
Страница 8: ...AVTMMTO210 Rev 7 Sept 2013 iv M...
Страница 18: ...M AVTMMTO210 Rev 7 Sept 2013 10 M...
Страница 22: ...M AVTMMTO210 Rev 7 Sept 2013 14 M...
Страница 32: ...M AVTMMTO210 Rev 7 Sept 2013 24 M...
Страница 48: ...M AVTMMTO210 Rev 7 Sept 2013 40 M...
Страница 72: ...M AVTMMTO210 Rev 7 Sept 2013 64 M...
Страница 74: ...M AVTMMTO210 Rev 7 Sept 2013 66 M...