energized, the operating compressor on that refrigerant circuit will operate until the low pressure
switch opens and stops that compressor. The compressor will cycle on if the evaporator pressure
exceeds the low pressure cut-in value. After a two hour time delay, the compressor will start again to
pump down the circuit (limited recycling pumpdown). After a two hour time delay, the compressor
will start if the Global UNT controller calls for cooling.
The Pumpdown and Stop switch will open its respective circuit’s digital input to the Global UNT
controller. This will open the associate circuit’s output and open the circuit’s solenoid valve. If a
compressor is operating on that circuit, the compressor will operate until the low pressure switch
stops the compressor. If a compressor is not running, the switch does not activate a pumpdown for
that circuit but will not allow the circuit to stage on and operate.
Certain alarm conditions will not permit chiller pumpdown. These alarm conditions are:
•
High Condenser Pressure
•
Bad Evap Pressure Sensor
•
Compressor Motor Protect
•
Freezestat Alarm
•
Oil Pressure
•
Phase Voltage Monitor (optional)
•
Ground Fault (optional)
Freezestat Control
On startup the Global UNT controller will check the evaporator pressure after the SLPT(starting low
pressure time) timer times out. If the evaporator pressure is greater than the LPHL (low pressure high
limit) value, the Global UNT controller will continue to stage up as additional cooling is required. If
the evaporator pressure is less than the LPHL, the Global UNT controller will de-energize BO7 or
BO8 (depends on circuit starting) which will stop the compressor. This is a Freezestat alarm (alarm
will indicate on the optional Zone Terminal) and will require the resetting by depressing the
FREEZESTAT RESET on the control panel. The circuit will not go through a pumpdown.
If the chiller has been operating and the evaporator pressure in either circuit is less than the LPFS
(low pressure Freezestat setpoint) the Global UNT controller starts the FSTP (Freezestat time period).
If the evaporator pressure is below the LPHL after the FSTP times out, BO7 or BO8 (depends on
evaporator circuit with the low pressure) will be de-energized stopping the operating compressor(s)
and closing that refrigerant circuit’s liquid line solenoid valve. This is a Freezestat alarm (alarm will
indicate on the optional Zone Terminal) and will require the resetting by depressing the
FREEZESTAT RESET on the control panel. There is a five-minute time delay after the freezestat
reset switch has been depressed. The circuit will not go through a pumpdown upon alarm.
Starting Timers
The Global UNT controller has a starting timer which delays checking the evaporator pressure for
260 seconds. After the timer times out, the evaporator pressure is checked. If the pressure is above
the LPHL (low pressure high limit, (default 57psi)) value, the controller stages up on leaving water
temperature requirements. If the evaporator pressure is below the LPHL, then the controller will stop
that circuit and indicate a freezestat alarm on the (optional) Zone Terminal.
Содержание AGR 070AS
Страница 20: ...20 AGR 070A through 100A IOMM AGR 1 Figure 9 Typical Field Wiring with Global UNT Controller...
Страница 21: ...IOMM AGR 1 AGR 070A through 100A 21 Figure 10 Typical Field Wiring Diagram with MicroTech Controller...
Страница 22: ...22 AGR 070A through 100A IOMM AGR 1 Figure 11 Standard Single Point Connection with FanTrol...
Страница 23: ...IOMM AGR 1 AGR 070A through 100A 23 Figure 12 Standard Single Point Connection with Optional SpeedTrol...
Страница 24: ...24 AGR 070A through 100A IOMM AGR 1 Figure 13 Unit Control Schematic 2 compressor UNT...
Страница 25: ...IOMM AGR 1 AGR 070A through 100A 25 Figure 14 Staging Schematic 2 compressor 4 stage UNT...
Страница 26: ...26 AGR 070A through 100A IOMM AGR 1 Figure 15 Staging Schematic 2 compressor 6 stage UNT...
Страница 27: ...IOMM AGR 1 AGR 070A through 100A 27 Figure 16 MicroTech Controller Schematic...
Страница 28: ...28 AGR 070A through 100A IOMM AGR 1 Figure 17 Unit Control Schematic MicroTech...
Страница 29: ...IOMM AGR 1 AGR 070A through 100A 29 Figure 18 Staging Schematic 4 stage MicroTech...
Страница 30: ...30 AGR 070A through 100A IOMM AGR 1 Figure 19 Staging Schematic 6 stage MicroTech...
Страница 31: ...IOMM AGR 1 AGR 070A through 100A 31 Figure 20 Unit Control Schematic 2 compressor MicroTech...
Страница 32: ...32 AGR 070A through 100A IOMM AGR 1 Figure 21 UNT Instrument Layout See legend on page 34...
Страница 33: ...IOMM AGR 1 AGR 070A through 100A 33 Figure 22 MicroTech Instrument Layout See legend on page 34...
Страница 35: ...IOMM AGR 1 AGR 070A through 100A 35 Figure 25 MicroTech Sensor Layout...
Страница 99: ...IOMM AGR 1 AGR 070A through 100A 99 Notes...
Страница 100: ...Post Office Box 2510 Staunton Virginia 24402 USA 800 432 1342 www mcquay com...