46
AGR 070A through 100A
IOMM AGR-1
Digital Inputs
Note:
All Digital Inputs are 24 VAC supplied by transformer T2 in the control panel. Do not
use inputs from another power supply external to the unit. This can cause failure of the
Global UNT controller.
Table 13, Digital Inputs
Input
Description
Location
Closed
Open
BI-1
Time Clock
Field Installed to TB-7 #140 & #141
Run
Stop
BI-2
Auto / Pumpdown and Stop Switch Circuit #1
Control Panel
Run
Pumpdown
Stop
BI-3
Auto / Pumpdown and Stop Switch Circuit #2
Control Panel
Run
Pumpdown
Stop
BI-4
Chilled Water Flow Switch
Field Installed to TB-7 #142 & #143
Run
Stop
Relay Outputs
All of the relay outputs are controlled by the Global UNT controller. The relays are double pole
double throw relays with contacts rated for 120VAC - 7.0 amp and a 24 VAC holding coil. Refer to
the unit staging schematic.
Table 14, Relay Board Outputs
Relay Output
Number
Output
Description
1
Circuit #1 Liquid Line Solenoid Valve
2
Circuit #2 Liquid Line Solenoid Valve
3
Compressor #1 Unloader #1
4
Compressor #2 Unloader #1
5
Compressor #1 Unloader #2 (6-stage)
6
Compressor #2 Unloader #2 (6-stage)
7
Low Pressure Relay Circuit #1
8
Low Pressure Relay Circuit #2
Reset Options
The Global UNT controller is capable of one reset option. The reset option should be selected at the
time of purchase. Outside Air is the standard option and a Zone Terminal is necessary to activate this
option or any other reset option. Other reset options are available and requires a software download.
Field modifications can be accomplished with the Global UNT Interface Kit.
Outside Air Reset
When selected, a Outdoor Air Temperature (OAT) sensor is connected to TB-7 terminals #134 and
#135. Four variables are used to setup the reset ramp that calculates the Actual Leaving Water
Setpoint. These are: Leaving Water Setpoint (AI-4), Reset Band selected with a Zone Terminal,
Outdoor Air High Limit (OAHL), and Outdoor Air Reset Band (OARB).
Содержание AGR 070AS
Страница 20: ...20 AGR 070A through 100A IOMM AGR 1 Figure 9 Typical Field Wiring with Global UNT Controller...
Страница 21: ...IOMM AGR 1 AGR 070A through 100A 21 Figure 10 Typical Field Wiring Diagram with MicroTech Controller...
Страница 22: ...22 AGR 070A through 100A IOMM AGR 1 Figure 11 Standard Single Point Connection with FanTrol...
Страница 23: ...IOMM AGR 1 AGR 070A through 100A 23 Figure 12 Standard Single Point Connection with Optional SpeedTrol...
Страница 24: ...24 AGR 070A through 100A IOMM AGR 1 Figure 13 Unit Control Schematic 2 compressor UNT...
Страница 25: ...IOMM AGR 1 AGR 070A through 100A 25 Figure 14 Staging Schematic 2 compressor 4 stage UNT...
Страница 26: ...26 AGR 070A through 100A IOMM AGR 1 Figure 15 Staging Schematic 2 compressor 6 stage UNT...
Страница 27: ...IOMM AGR 1 AGR 070A through 100A 27 Figure 16 MicroTech Controller Schematic...
Страница 28: ...28 AGR 070A through 100A IOMM AGR 1 Figure 17 Unit Control Schematic MicroTech...
Страница 29: ...IOMM AGR 1 AGR 070A through 100A 29 Figure 18 Staging Schematic 4 stage MicroTech...
Страница 30: ...30 AGR 070A through 100A IOMM AGR 1 Figure 19 Staging Schematic 6 stage MicroTech...
Страница 31: ...IOMM AGR 1 AGR 070A through 100A 31 Figure 20 Unit Control Schematic 2 compressor MicroTech...
Страница 32: ...32 AGR 070A through 100A IOMM AGR 1 Figure 21 UNT Instrument Layout See legend on page 34...
Страница 33: ...IOMM AGR 1 AGR 070A through 100A 33 Figure 22 MicroTech Instrument Layout See legend on page 34...
Страница 35: ...IOMM AGR 1 AGR 070A through 100A 35 Figure 25 MicroTech Sensor Layout...
Страница 99: ...IOMM AGR 1 AGR 070A through 100A 99 Notes...
Страница 100: ...Post Office Box 2510 Staunton Virginia 24402 USA 800 432 1342 www mcquay com...