Equipment and Cable Installation for Metropolis
®
DMXtend
Shelf Horizontal Bay Mount
Final Operations
...........................................................................................................................................................................................................................................................
1 - 8 7
Lucent Technologies - Proprietary
See notice on first page
365-372-327 R2.0
Issue 1, October 2003
............................................................................................................................................................................................................................................................
Final Operations
Description
Final check on equipment and cable installation.
............................................................................................................................................................................
Procedure
Step 1
Verify that all the cables are properly dressed/connected.
............................................................................................................................................................................
Step 2
Verify that all cables are properly labeled.
............................................................................................................................................................................
Step 3
Verify that designations where cables were wire-wrapped are properly
labeled.
............................................................................................................................................................................
Step 4
Verify that all the fibers are properly dressed/connected.
............................................................................................................................................................................
Step 5
Verify that all fibers are properly labeled. See Appendix F, Fiber
Labeling
............................................................................................................................................................................
Step 6
Verify that designations where fibers were terminated are properly
labeled.
............................................................................................................................................................................
Step 7
Check off the appropriate box in Appendix E, Installation Checklist.
...........................................................................................................................................................................
End of Steps