Test Run
Installation Manual
67
ENGLISH
7. Test Run
1. Test run should be performed after auto-addressing
2. Test run can be performed when 3 minutes passed after power on, by DIP switches and but-
tons.
- needs time for initializing data of micom and readying communication with indoor unit.
3. 7-segment of outdoor unit displays test run status and error.
4. During test run, if error occurs, then test run ends and proceeds final stage of test run
- system should be initial status by initializing all data of test run pressing black button for 2 sec-
onds after all DIP switch off
5. In case of finishing test run during test run, press black and red button simultaneously for
5 seconds.
6. When test run is finished, indoor units are stopped and 938 is displayed after 90 seconds.
7. To perform FDD logic test, proceeds when 3 minutes passed after reset.
Step 0. Check order signal
Select the function of tust run
Step 1. Sensor checking
Check sensor abnormality.
Step 2. Refrigerant auto charging
In case of adding additional refrigerant, this function helps adding refrigerant automatically.
Step 3. Refrigerant checking
Check refrigerant amount is proper.
Checks before Test Run
Test Run Procedure
CAUTION
when cutting main power of the Air-to-Water Heat Pump
• Always apply main power of the outdoor unit during use of product
(cooling season/heating season).
• Always apply power 6 hours in advance to heat the crank case heater where
performing test run after installation of product. It may result in burning out of
the compressor if not pre-heating the crank case with the electrical heater for
more than 6 hours.(In case of the outdoor temperatue below 10°C)