95
Electrical System Installation
Due to our policy of continuous product innovation, some specifications may change without notification.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Table 16: Field-Installed Wiring / Cable Connections.
Table 15: Power Wiring System to Multiple, Grouped Chillers.
Circuit Breaker
Circuit Breaker
Circuit Breaker
Main Power Supply
Circuit Breaker
Main Power Supply
Refer to the wiring diagram for field-installed wiring. Only the main panel (HMI installed panel) requires wiring at the site. The control box is
shipped fully wired from the factory.
5. Circuit Breaker and Power Wiring Connections.
• Each chiller must have its own circuit breaker and direct power
wiring.
•
Do not install one circuit breaker for multiple chillers.
Do
not daisy chain the power wiring from the main power supply to
multiple chillers.
• Always label each circuit breaker and its connected chiller.
• Refer to the specification and electrical data when selecting circuit
breaker capacities. Follow all state, local, and NEC guidelines
when choosing and installing circuit breakers and power wiring.
ELECTRICAL
Wiring / Cable Installation
Index
Signal type
Location
Remarks
Power
DC Power
12 V DC
Necessary
Central control communication
Communication
CH2 A, B
Necessary
HMI communication
Communication
CH3 A, B
Necessary
Modbus
Communication
CH4 A, B
Optional (Field connection)
Ambient thermistor
DI
UI1, G
Necessary
Flow switch
DI
UI5, G
Necessary
(Except H/P model)
Pump interlock
DI
UI6, G
Optional (Field connection)
Remote On/Off
DI
DI1, GND
Optional (Field connection)
Remote CO/HP
DI
DI2, GND
Optional (Field connection)
Remote alarm
DI
DI3, GND
Optional (Field connection)
Alarm status
DO
DO1, COM
Optional (Field connection)
On/Off status
DO
DO2
Optional (Field connection)
Pump output
DO
DO3
Optional (Field connection)
Heater output
DO
DO5
Optional (Field connection)
Water spray output
DO
DO6
Optional (Field connection)
Global water inlet sensor
AI
UI3, GND
Optional (Field connection)
Global water outlet sensor
AI
UI4, GND
Optional (Field connection)
Remote Target Temp
AI
UI7, GND
Optional (Field connection)
Remote Demand Limit
AI
UI8, GND
Optional (Field connection)