3.13 Installing the upper section
Depending on installation depth, the upper section (insertion depth of the
upper section <3>) must be cut to length or given recesses
<67> for the pipe connections which are routed into the drain body
<1> at the side.
The upper section <3> may only be extended using a maximum of
2 extension sections, so that technicians can still reach down to the
drain body for maintenance purposes.
- Insert the sealing gasket <37> grease-free into the groove on the drain
body <1>.
- Grease the sealing lips of the sealing gasket <37>.
- Push the upper section <3> into the drain body and align it.
3.14 Installing the inflow cover
This is fitted to protect the drain from soiling
through e.g. construction material.
For this:
- Keep the sealing area clean
- Grease the outside of the sealing gasket
• Insert the inflow cover <51> into the upper section <3>.
• Close both cover closures <78>.
3
67
37
1
Fett
Fig. [19]
3
51
78
Fig. [20]
Содержание Ecolift
Страница 22: ...22 144 DOP Leistungserkl rung 04 2017 6 DOP Leistungserkl rung...
Страница 23: ...DOP Leistungserkl rung 23 144 04 2017...
Страница 46: ...46 144 Declaration of performance 04 2017 6 Declaration of performance...
Страница 47: ...Declaration of performance 47 144 04 2017...
Страница 71: ...D claration de performance 71 144 04 2017 6 D claration de performance...
Страница 94: ...94 144 DoP Dichiarazionediprestazione 04 2017 6 DoP Dichiarazione di prestazione...
Страница 95: ...DoP Dichiarazionediprestazione 95 144 04 2017...
Страница 118: ...118 144 DOP vermogensverklaring 04 2017 6 DOP vermogensverklaring...
Страница 119: ...DOP vermogensverklaring 119 144 04 2017...
Страница 142: ...142 144 DOP Deklaracja w a ciwo ci u ytkowych 04 2017 6 DOP Deklaracja w a ciwo ci u ytkowych...
Страница 143: ...DOP Deklaracja w a ciwo ci u ytkowych 143 144 04 2017...