Sleeve-type bolts
1
2
3
4
5
6
Item Description
1.
Baseplate
2.
Shims
3.
Foundation
4.
Sleeve
5.
Dam
6.
Bolt
Figure 2: Sleeve type bolts
J-type bolts
1
3
2
4
5
Item Description
1.
Baseplate
2.
Shims or wedges
3.
Foundation
4.
Dam
5.
Bolt
Figure 3: J-type bolts
4.1.2 Sub-base Leveling
Grouted Base
When the unit is received with the pump and driver mounted to the sub-base, it should be placed on the
foundation and the coupling halves or V-belts disconnected (see Figure titled
Sub-base, top view
). The
coupling should not be reconnected until all realignment operations have been completed. A recom-
mended coupling alignment procedure is included in the following sections.
4.1 Preinstallation
Model AF (42"/1200mm/54"/60"/66") LM/LMR Bearings Installation, Operation, and Maintenance Manual
17