6.1 Checking the unit
This section contains instructions on how to make the unit work once correctly wired and closed.
INGECON
SUN SMART TL units manage a generating installation or part of one. The correct condition of this
installation must be checked before start-up.
Each installation is different, depending on its characteristics, the country in which it is located or other special
conditions which may apply. In any case, before starting up, it is necessary to ensure that the installation complies
with the applicable legislation and regulations and that at least the part to be started up is complete.
6.1.1 Inspection
Before inverter start-up, a general inspection of the units must be carried out involving mainly:
· Check that the cables are
correctly connected to their connectors at the bottom of the housing. Check
also that
these cables are in a good condition and that there are no hazards in their environment which damage them, such
as sources of intense heat, objects which could cut them or arrangements which put them at risk of impacts or pulls.
- Removing the perspex-type protections for performing this inspection is strictly forbidden.
- If you have chosen to incorporate DC or AC arresters, check that they are correctly installed in their bases and that
the “status window” is not red (see ‘Kits and accessories’).
·
Check that the unit is firmly fixed and there is no danger of it falling off.
· Check that the isolating switch is in the ON position.
6.1.2 Sealing of the unit
During installation, make sure that the protection grade of the equipment has not been altered.
In all connections through cable glands, give cabling enough length inside the unit so it does not pull on the internal
electrical connection terminals.
Ensure that the cutouts not used have been properly sealed.
Safety measures
The front door should be opened only after disconnecting the unit from the grid and the PV array.
It is also essential to close the unit before connecting it to the PV array or the mains.
The guarantee does not cover damage caused by inadequate sealing of the unit.