4 - MOVEMENT AND INSTALLATION VIP80E-II
4 - Pag. 10 / 22
4.6.4 Bar feeder fastening
GROUND FASTENING
• Drill the floor and fix the lifting foot
with expansion plugs.
• Check the levelling and alignment once
more.
• Remove all the equipment used for the
levelling and alignment phases and
restore the initial bar feeder
conditions.
4.7
BAR FEEDER INSTALLATION (with displacement)
WARNING - CAUTION:
the installation and connections must be carried out according to the indications
provided by the manufacturer. The responsible person will also take into
account all regulative and law requirements, carrying out all the installations
and connections workmanlike. Once the installation has been completed, and
before the operating phases, he will check if the above-mentioned requirements
have been fulfilled.
The installation area must be in adequate environmental conditions (luminosity, ventilation,
etc.).
The floor must be steady and leveled in order to allow a correct fastening of the bar feeder.
If necessary locate the exact position by drawing the coordinates.
MAX 150
ł
14
8070_04_11_1
Содержание VIP80E-II
Страница 2: ......
Страница 4: ......
Страница 6: ......
Страница 8: ......
Страница 10: ......
Страница 16: ...EN 1 INFORMATIONS GÉNÉRALES VIP80E II 1 Pag 6 6 ...
Страница 21: ...2 TECHNICAL INFORMATION VIP80E II EN 2 Pag 5 28 P Electric cabinet houses the electrical control panel ...
Страница 44: ...EN 2 TECHNICAL INFORMATION VIP80E II 2 Pag 28 28 ...
Страница 50: ...EN 3 SAFETY PROCEDURES GENERAL INFORMATION VIP80E II 3 Pag 6 6 ...
Страница 80: ...EN 5 ADJUSTMENTS AND SETUP VIP80E II 5 Pag 8 8 ...
Страница 98: ...EN 7 BAR FEEDER MAINTENANCE VIP80E II 7 Pag 4 6 7 4 GREASING POINTS 8070_07_03_1 Grease Grease ...
Страница 100: ...EN 7 BAR FEEDER MAINTENANCE VIP80E II 7 Pag 6 6 ...
Страница 104: ...EN 8 TROUBLES CAUSES CURES VIP80E II 8 Pag 4 4 ...