UPS5000-E-(50 kVA-300 kVA)
User Manual (50 kVA Power Modules)
3 Installation
Issue 02 (2017-02-25)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
47
Tools and Meters
Torque screwdriver
Cable cutter
Brush
Flat-head
screwdriver
(2–5 mm)
Phillips screwdriver
(M3/M4/M5/M6/M
8)
Insulated torque
wrench
(M6/M8/M12/M16)
Heat shrink tubing
Insulated adjustable
wrench
lists only the common tools for installation and cable connection. For more dedicated tools
required, see the corresponding component manuals. Prepare tools based on site requirements.
3.1.3 Preparing Power Cables
The UPS can generate large leakage currents. A circuit breaker that provides leakage
current protection is not recommended.
If multiple UPSs are to be connected in parallel, input and output power cables for each
UPS should have the same length and specifications.
The TN-C system is supported when the input N and PE are connected. For the connecting
method, see
A (Optional) TN-C System Application
lists the recommended cross-sectional areas for power cables. Note that the currents
listed are measured at a rated voltage of 380 V.