Installing the RTN 310
1.
Cover unused ports with caps/PG covers. Retain removed caps for future use.
2.
Before installing the RTN 310, remove the protective cover and film on the antenna port. Otherwise, signal transmission will be affected.
3.
Different methods can be used to change the polarization direction of antennas. If the method provided in this document is not suitable for the type of antennas you have, use the method provided in the installation manual delivered with your antennas.
4.
The default polarization direction of antennas is vertical. If the planned polarization direction is horizontal, change the polarization direction to horizontal.
5.
If an antenna with a diameter of 0.6 m or less is used in a direct mounting scenario, you may install the RTN 310 on the antenna and then hoist them both into position on the tower.
6.
Before installing a cable, bind the cable section that links the cable connector to the pole. This will protect the cable connector from damage. Be sure that the length of cable running from the binding point to the RTN 310 is sufficient to attach the cable connector to the
Ethernet service port on the RTN 310.
2
Installing the RTN 310 at the Edge of a Mobile Backhaul Network (Outdoor PI Used)
Optional
:
Change the polarization direction
of the antenna to horizontal if required.
Follow the antenna installation guide to
install the antenna.
Install the PGND cable of the
RTN 310.
Optional
:
Install an outdoor fiber.
• Install a ground clip.
1
2
Apply petroleum jelly around the exterior
side of the feed.
3
Install the RTN 310 on the antenna.
4
5
6
7
Install a GE cable.
• Select a ground point for the GE cable.
Install a PI and cables on the PI.
8
Power on the RTN 310.
11
Use a USB flash drive to load
NE data.
12
Use the Web LCT to
configure NE data.
13
Align antennas.
14
Waterproof the ground clip.
9
Check the installation.
10
• Lay out the GE cable.
• Install an outdoor fiber on the RTN 310.
• Lay out the outdoor fiber.
• Attach a yellow label to the fiber
according to the plan.
16/17 >>
• Install a GE cable.
• Attach a yellow label to the cable
according to the plan.
Installation procedure
Site commissioning procedure
•The GE(o) port and COMBO port can
transmit/receive GE (optical) services.
•The P&E port can transmit/receive GE (electrical)
services.
•The RTN 310 provides power over Ethernet
through the P&E port.
Transmits/Receives one channel
of FE/GE (electrical) service.
P&E
P&E1
Grounded using a
ground clip
Connected to the
power supply device
GE(o)
5
6
7
8
Grounded using
a ground clip
GE1
11
1 to 4
Transmits/Receives one channel
of GE (optical) service.
For the installation method, see the PI
installation guide.